The same arithmetic the dashboard applies to your live data, without connecting anything — from the forecast at completion and the WIP check to bid pricing, change orders and pay applications — plus material quantities for concrete, gravel, drywall, roofing, paint, brick and block, and asphalt, and the safety rates a prequalification asks for. Pick the question you have today.
Enter the budget, what you have spent and how far along the work is. You get the forecast two ways — performance-based and burn-based — and the verdict tells you when the two disagree, because that is usually the first sign of an overrun.
Earned value = BAC × % complete. CPI = EV ÷ AC (below 1 means you are paying more than the work is worth). EAC (performance) = BAC ÷ CPI. EAC (burn) = AC + (spend ÷ 3) × months remaining. VAC = BAC − EAC. TCPI = what the remaining work must achieve to still land on budget — above 1.1 is usually not going to happen. Months to exhaustion = (BAC − AC) ÷ monthly burn.
Over-billing improves cash and hides coming losses; under-billing starves the job of cash while the work is happening. This is the check a controller runs before agreeing the month.
% complete (cost method) = cost to date ÷ estimated cost at completion. Revenue earned = contract × % complete. Over/under billing = billed to date − revenue earned: positive is over-billed (cash ahead of the work), negative is under-billed. Retention held = billed × retention %. Cash position = billed to date − cost to date.
Upload the schedule you already have — PDF, Excel or CSV from Primavera P6, Microsoft Project, Smartsheet or Procore — or paste it in. The tool pulls the activity table out of the file and recognises the columns from their headers, so you do not have to rename anything. It then tells you which activities are behind, over budget, or both.
Recognised headers: activity / task / description · start · finish / end · % complete / percent
complete / progress · budget / cost / planned cost · actual / actual cost / cost to date. Dates can be
yyyy-mm-dd, dd/mm/yyyy or mm/dd/yyyy.
An activity is behind when its finish date is in the past and it is not 100% complete (drawn from the plan's own dates), over budget when actual cost exceeds its budget at completion, and at risk when it is both. Forecast cost at completion for the plan = actual to date + remaining budget on the unfinished activities.
A journeyman at $42 an hour does not cost $42 an hour. Burden, fringe and payroll taxes usually add thirty to forty percent, and overtime adds half again on top of that. This is the number to use when you price a change order or decide whether the weekend is worth it.
Loaded rate = base × (1 + burden%) + fringe. Straight-time cost = loaded × hours. Overtime premium = base × 0.5 × OT hours (the half again that overtime adds — the other half is the hour the crew would have worked anyway). Double-time premium = base × 1.0 × DT hours. True cost per hour = total ÷ hours, which is the figure to use when you compare it with a budget line that was priced at base rate.
Markup and margin are not the same number, and pricing a 20% margin with a 20% markup leaves money on the table on every job. Enter your costs and the margin you want to keep.
Cost basis = direct cost × (1 + overhead %). Bid price = cost basis ÷ (1 − margin % − bond %). Markup = (bid − direct cost) ÷ direct cost. Margin = profit ÷ bid. A 20% margin needs a 25% markup; a 20% markup is only a 16.7% margin.
Price the change the way the contract lets you: each cost type with its own markup, then bond and insurance on top. The breakdown is what the owner's rep will ask to see.
Self-performed = labor + material + equipment, marked up at the self-performed rate. Subcontract is marked up at its own (usually lower) rate. Bond and insurance apply to the subtotal. Check your contract's change-order clause for the markups it allows.
The arithmetic behind a G702-style pay application: work completed and stored to date, retainage held, what was already billed, and what is due this period.
Completed and stored = contract × % complete + stored materials. Retainage = completed work × retainage % + stored × stored-retainage %. Earned less retainage = completed and stored − retainage. Current payment due = earned less retainage − previous certificates. Balance to finish = contract − completed and stored, plus retainage.
Every job has to carry its share of the office, the yard and the trucks. This works out the markup your overhead needs, and the revenue where the company stops losing money.
Overhead rate = overhead ÷ revenue. Required gross margin = overhead rate + target net profit. Required markup on cost = required margin ÷ (1 − required margin). Break-even revenue = overhead ÷ gross margin — below it, jobs do not earn enough to pay for the office.
Slab, footing, wall or round column: enter the dimensions and how many there are, and get the volume with waste, the number of premix bags, the truckloads, and the cost at your price per yard.
Volume (ft³) = length × width × thickness ÷ 12, or π × (diameter ÷ 24)² × height for a column, × how many. Cubic yards = ft³ ÷ 27, then × (1 + waste %). Bags: an 80 lb bag of premix yields about 0.60 ft³, a 60 lb bag 0.45 ft³ and a 40 lb bag 0.30 ft³. Truckloads assume 10 yd³ per truck. Check bag yields on the bag you buy.
Base courses, driveways, pipe bedding, topsoil: enter the area and the depth, choose the material, and get the cubic yards, the tons to order after compaction, the truckloads and the cost.
Compacted volume = length × width × depth ÷ 12 ÷ 27 cubic yards. Loose volume to order = compacted × (1 + compaction %). Tons = loose cubic yards × density. Densities are typical figures for dry material; wet or washed stone weighs more — your quarry’s scale ticket is the real number.
Enter the room or the total wall length, the height and the openings, and get the board area, the number of sheets in the size you hang, and the finishing materials to order with it.
Board area = wall length × height + ceiling − 21 sq ft per door − 15 sq ft per window. Sheets = board area × (1 + waste %) ÷ sheet area, rounded up. Finishing materials use common planning rates per 1,000 sq ft of board: about 370 ft of paper tape, 140 lb (≈ 2.3 boxes) of ready-mixed all-purpose compound for a level 4 finish, and about 1,000 screws. Your finisher’s own rates are better.
Enter the footprint of the roof including overhangs and its pitch, and get the true roof area, the roofing squares with waste, shingle bundles, underlayment rolls and the material cost.
Pitch factor = √(1 + (rise ÷ 12)²): 1.118 at 6/12. Roof area = footprint × pitch factor — this holds for gable and hip roofs of one pitch. Squares = roof area ÷ 100, then × (1 + waste %). Bundles = squares × bundles per square, rounded up. Underlayment assumes synthetic rolls of 10 squares (1,000 sq ft); #15 felt rolls cover about 4 squares.
Enter hours worked and the cases on your OSHA 300 log to get the incident rates every prequalification form asks for — on the 200,000-hour basis — plus what your experience modifier does to the workers' comp premium.
Rate = cases × 200,000 ÷ hours worked — 200,000 hours is 100 full-time workers for a year. TRIR counts every recordable case, DART the cases with days away, restriction or transfer, LTIR the cases with days away. Severity rate = lost workdays × 200,000 ÷ hours. Modified premium = manual premium × EMR; the modifier is calculated by your rating bureau (NCCI or the state's) from three policy years of losses, so this shows its cost, not the modifier itself.
Enter the room or area — wall perimeter and height, ceiling area, openings — and the coats, and get gallons of wall and ceiling paint, the cost, and the labor hours at your production rate.
Wall area = perimeter × height − 21 sq ft per door − 15 sq ft per window. Gallons = area × coats ÷ coverage, rounded up separately for walls and ceilings (they are usually different products). Labor hours = (wall + ceiling area) × coats ÷ production rate — painting only; add prep, masking and access separately.
Enter the wall and the unit, and get the net wall area, the bricks or concrete blocks to order with waste, the mortar bags and the material cost.
Net area = length × height − openings. Units = net area × units per sq ft (with 3/8 in joints), then × (1 + waste). Mortar = units ÷ 100 × bags per 100 units — a planning figure; joint size, unit type and the mix change it, so confirm with the mortar maker's yield table. Single wythe; double it for a two-wythe wall.
Enter the area and the compacted thickness, and get the tons of hot mix asphalt to order, the square yards, truckloads and the material cost.
Volume = length × width × thickness ÷ 12 (cu ft). Tons = volume × density ÷ 2,000, then × (1 + waste). At 145 lb/cu ft that is about 110 lb per square yard per inch of thickness — the figure most paving estimates use as a check.
Pick the bar size, enter how many bars and how long, and get the weight in pounds and tons, the linear feet with lap and waste, and the number of stock bars.
Linear feet = bars × length × (1 + lap and waste). Weight = linear feet × pounds per foot for the bar size. Rebar is sold by weight, so the weight drives the cost; stock bars = linear feet ÷ stock length, rounded up.
Enter the thickness, width and length of each piece and how many there are, and get the board feet, the cost at your price per board foot and the cubic feet.
One board foot is a piece 1 in thick, 12 in wide and 12 in long: 144 cubic inches. Board feet = thickness (in) × width (in) × length (ft) ÷ 12, times the number of pieces. Lumber is sold by its nominal size, so a 2×10 is counted as 2 × 10.
Enter the total rise and your target riser height, and get the number of risers and treads, the exact riser height, the total run, the stringer length and the angle.
Risers = total rise ÷ target riser, rounded to a whole number. Riser height = total rise ÷ risers, so every riser is equal. Treads = risers − 1 (the floor above is the last step). Total run = treads × tread depth. Stringer length = √(rise² + run²).
Enter the room and the tile or plank size, and get the area with waste, the number of pieces, the boxes to order and the cost.
Area = length × width. Order area = area × (1 + waste). Pieces = order area × 144 ÷ (tile width × tile length). Boxes = order area ÷ square feet per box, rounded up, because flooring is sold by the box.
Enter one or two rectangles and any area to deduct, and get the total square feet, square yards, square meters and acres.
Area = (length 1 × width 1) + (length 2 × width 2) − deductions. One square yard is 9 square feet, one square meter is 10.764 square feet and one acre is 43,560 square feet.
Enter the wall length and height and the block size, and get the courses, the blocks and caps to order, the base gravel, the drainage backfill and the block cost.
Courses = height × 12 ÷ block height, rounded up. Blocks = courses × blocks per course × (1 + waste), where blocks per course = length × 12 ÷ block length. Caps = blocks per course. Base gravel = length × trench width × depth ÷ 27 (cubic yards); backfill = length × height × backfill width ÷ 27.
Enter the loan, the rate, the build time and how much of the loan is drawn on average, and get the interest during construction and the monthly payment once it converts.
Interest during construction = loan × average share drawn × rate × months ÷ 12. Interest-only payment at full balance = loan × rate ÷ 12. Permanent payment = loan × r ÷ (1 − (1 + r)^−n), where r is the monthly rate and n the number of months.
Yes, and they run entirely in your browser — nothing you type is sent anywhere. They are the same arithmetic the Constructelligence dashboard applies to your live data.
Two ways, shown side by side: budget ÷ cost performance index, and actual cost plus the remaining months at the recent burn rate. When the two disagree by more than ten percent, the job is worth looking at.
Paste or upload rows from a Primavera P6, Microsoft Project, Smartsheet or Procore activity export. The tool matches the column headers it finds, so the same sheet works without renaming anything.
These tools are manual. The dashboard does the same arithmetic across every job, every company and every week — plus the money-at-risk view, the audit findings and the overrun radar. Join the private beta and we will connect it to the systems you already run.