Change order pricing calculator
Price a change order the way the contract allows: self-performed work marked up at one rate, subcontracted work at another, and bond and insurance on top. Enter the scope and get the number to put on the request — and the blended markup it works out to.
Change order pricing
Price the change the way the contract lets you: each cost type with its own markup, then bond and insurance on top. The breakdown is what the owner's rep will ask to see.
Change scope
Result
Self-performed = labor + material + equipment, marked up at the self-performed rate. Subcontract is marked up at its own (usually lower) rate. Bond and insurance apply to the subtotal. Check your contract's change-order clause for the markups it allows.
How to use it
- Enter labor hours and the loaded rate.
- Enter material, equipment and subcontract cost.
- Enter the markups your contract allows on self-performed and subcontracted work.
- Enter bond and insurance, and read the price.
A worked example
Questions
How do you price a construction change order?
Cost the labor, material, equipment and subcontract work, apply the markups the contract allows to each, then add bond and insurance.
What markup is allowed on change orders?
It is set by the contract’s change-order clause — often one rate on self-performed work and a lower rate on subcontracted work. Check the contract before pricing.
Should overtime go in a change order?
If the change requires it, yes — at the premium cost, with the reason documented.
How do I stop carrying unsigned change orders?
Price and send the request quickly, track cost coded to it as unsigned work in place, and escalate anything pending more than 30 days.