Constructelligence
Constructelligence › Free tools › Labor burden & overtime

Fully burdened labor rate calculator for construction

The wage on the timecard is not what an hour of labor costs. Add payroll burden and fringe to get the fully burdened (or fully loaded) hourly rate, then see what overtime and double time really add across a crew — the figure to compare with a budget line priced at base rate.

Free, no sign-upRuns in your browser — nothing is sent anywhereFormulas shownCopy a link to share your numbers
Tool 04

Labour burden and overtime premium

A journeyman at $42 an hour does not cost $42 an hour. Burden, fringe and payroll taxes usually add thirty to forty percent, and overtime adds half again on top of that. This is the number to use when you price a change order or decide whether the weekend is worth it.

Crew inputs

Result

Loaded rate = base × (1 + burden%) + fringe. Straight-time cost = loaded × hours. Overtime premium = base × 0.5 × OT hours (the half again that overtime adds — the other half is the hour the crew would have worked anyway). Double-time premium = base × 1.0 × DT hours. True cost per hour = total ÷ hours, which is the figure to use when you compare it with a budget line that was priced at base rate.

How to use it

  1. Enter the base hourly wage.
  2. Enter payroll burden (taxes, insurance, workers’ comp) as a percentage, and fringe per hour.
  3. Enter straight-time, overtime and double-time hours for a week.
  4. Enter crew size to see the weekly cost across the crew.

A worked example

A $42 base wage with 32% burden and $12 fringe is a $67.44 loaded rate. Ten overtime hours add $210 of premium per worker — for a crew of eight, $1,680 a week that a base-rate budget never saw.

What goes into labor burden

ItemHow it is charged
Social Security and Medicare (FICA)7.65% of wages — 6.2% Social Security up to the annual wage base, plus 1.45% Medicare
Federal unemployment (FUTA)0.6% of the first $7,000 per employee per year, after the usual state credit
State unemployment (SUTA)Your state's rate on its own wage base — it varies by state and by your claims history
Workers' compensationA rate per $100 of payroll for each class code, times your EMR
General liabilityOften rated on payroll for contractors
Benefits and fringesHealth, retirement, union fringes — per hour or per month
Paid time offHolidays, vacation and sick time paid for hours not worked

Payroll taxes and workers' comp are percentages of wages; fringes are usually a dollar amount per hour. That is why this calculator takes them separately.

Paid hours vs productive hours

A worker paid for 2,080 hours a year who takes 80 hours of holidays, 80 of vacation and 40 of training produces 1,880 hours on jobs. Every cost of the 2,080 paid hours has to be recovered from the 1,880 productive ones, so the rate charged to jobs rises by 2,080 ÷ 1,880 = 1.106 — about 11% — before any tax or insurance. Budgets built on the base wage alone miss both.

Burden rate vs loaded rate

The burden rate is the percentage added to wages for taxes, insurance and benefits. The loaded (or fully burdened) labor rate is the hourly figure that results — wage × (1 + burden %) + fringes per hour. Some contractors go one step further and add an overhead allocation per hour to get a billing rate; keep that separate, or overhead ends up counted twice when the bid adds markup.

Want the background? The guide works through the arithmetic, the mistakes that hide problems, and a checklist.
Read: Construction labor forecasting →

Questions

What is labor burden in construction?

The cost of employing someone on top of their wage: payroll taxes, workers’ compensation, unemployment insurance, benefits and other statutory costs, usually expressed as a percentage of wages.

How do you calculate a fully burdened labor rate?

Base wage × (1 + burden %) + fringe per hour. A $42 wage with 32% burden and $12 fringe is a fully burdened rate of $67.44 an hour. The same figure is called the fully loaded or loaded labor rate.

What is the difference between a burdened and a fully loaded labor rate?

Usage varies. Most contractors use both for wage plus payroll burden and fringe. Some add a share of company overhead to the fully loaded rate; if you do, add it as a percentage in the burden field and say so wherever the rate is used.

How much does overtime really cost?

The premium is half the base wage for each overtime hour (double time adds a full base wage), on top of the loaded cost of the hour itself.

What is a typical labor burden percentage?

It varies widely by trade, state and workers’ comp class; use your own payroll data rather than a rule of thumb.

More free calculators

Want this on your live data, every morning?

These tools are manual. The dashboard does the same arithmetic across every job, every company and every week — plus the money-at-risk view, the audit findings and the overrun radar. Join the private beta and we will connect it to the systems you already run.