Procore ERP integration: what syncs with your accounting system, and how

Procore holds the project side of a job — commitments, change orders, subcontractor invoices — and the ERP holds the books. Procore's ERP integration is the bridge, and it works differently from most syncs: records don't flow straight through, they wait for an accounting approver. This guide explains the mechanism from Procore's developer documentation, what moves in each direction, and the setup decisions that decide whether it stays in sync.

Updated · 10 minute read

Key takeaways
  • Procore's ERP integration stages records for an accounting approver in both directions.
  • Imports carry the ERP's Origin ID; that is what marks a record synced.
  • Masters (vendors, jobs, codes) flow ERP → Procore; commitments and invoices flow back.
  • Tie out committed cost per job monthly; unexplained differences are failed syncs.

How it works: a staging area with an approver

Procore's ERP Integrations tool is a company-level tool that acts as a staging area. Financial records from either side wait there until a user with accounting-approver permission accepts them:

The approval step is the point: money only reaches the books after someone in accounting has looked at it, and nothing enters Procore's financial tools without the ERP's ID.

ERPvendors · jobs · codes ERP Integrations toolstaging areaaccounting approver ✓ Procore project toolscommitments · invoices import → (carries the ERP's Origin ID)← export (approved commitments, invoices)
Nothing crosses without an accounting approver; imported records carry the ERP's ID, which is what marks them synced.

What syncs, and which way

RecordUsual directionWhy that way
VendorsERP → ProcoreVendor setup (tax IDs, insurance, payment details) belongs in the books
Jobs and sub jobsERP → ProcoreThe job number is created once, in the ERP
Cost codes and cost typesERP → ProcoreOne code structure, owned by accounting
BudgetsERP → ProcoreThe estimate's budget is loaded once, then tracked in both
Commitments (subcontracts, POs)Procore → ERPWritten and approved on the project, recorded in the books
Commitment change ordersProcore → ERPSame path as the commitment they change
Subcontractor invoicesProcore → ERPReviewed against the commitment in Procore, paid from the ERP
Payments and job costERP → ProcoreOnly the books know what was paid and posted

Which of these a given integration supports depends on the ERP and the connector; the table is the pattern Procore's framework is built around, not a promise for every pairing.

CalculatorCommitment tie-out
ERPthe booksProcorethe projectVendorsJobs & sub jobsCost codes & typesBudgetsCommitmentsCommitment COsSub invoicesSet up once in the books → flows to the project · written on the project → recorded in the books
The usual directions from the table in this section. Each record has one owner; the other side reads it.

Connector options

An integration built on this framework needs a service running outside Procore that talks to both systems — Procore notifies it through webhooks when something is sent for export. In practice that comes from one of three places:

Whichever you use, ask which records it syncs, in which direction, how often, and what happens to a record the ERP rejects.

Setup decisions that keep it in sync

  1. Make job numbers identical. The Procore project number should be the ERP job number exactly — reports, integrations and people all join on it.
  2. Import the cost code structure; never build it twice. Procore's standard cost codes and line item types should mirror the ERP's cost codes and categories, so commitment lines land on the budget lines they buy out.
  3. Sync vendors from the ERP only. Vendors created in Procore by hand won't carry an Origin ID and won't export cleanly.
  4. Name the accounting approvers and agree how fast they clear the staging area. A week-old queue means the ERP's committed cost is a week behind.
  5. Decide what happens to history. Commitments written before the integration existed may need importing with their Origin IDs, or they stay invisible to the ERP side.

Checking it: the monthly tie-out

Once live, compare the two systems per job each month:

Committed in Procore, job J-1104$2,180,000
Committed in the ERP, job J-1104$2,132,000
Difference$48,000
Explained: one change order waiting in the staging area$48,000
Unexplained$0

An explained difference is usually something waiting for approval. An unexplained one is a failed or skipped sync, and the job's committed cost and forecast are wrong in one of the two systems until it's found. Constructelligence reads both sides — Procore's commitments and Sage job cost — and shows them side by side per job, which makes this check a lookup rather than a spreadsheet.

Checklist
Procore ERP tieout in Excel, filled in with example rows — columns: Job, Committed in Procore, Committed in ERP, Difference, Waiting in staging, Unexplained, Note
The procore erp tieout as it opens in Excel: example rows in italics, calculated columns shaded.
Free template · Procore ERP tieout (Excel & CSV)An Excel workbook with drop-downs, validation and formulas built in — or the same columns as a CSV for Google Sheets and Numbers.
Download Excel (.xlsx)
What this template captures

Committed cost per job in Procore and in the ERP, the difference, what is waiting in staging and what is unexplained.

7 columns: 5 you fill in and 2 calculated by formula and filled down 200 rows, so nothing is worked out by hand. In the Excel version, 3 columns reject entries of the wrong type (a date column only takes dates, an amount column only numbers), the header row stays frozen with filters on it, and the workbook opens on an Instructions sheet that lists every column below.

Every column, and how it is captured
ColumnTypeWhat goes in it
JobTextJob number exactly as in your accounting system (e.g. J-1104), so rows join to job cost.
Committed in ProcoreAmount ($)Enter the amount in dollars.
Committed in ERPAmount ($)Enter the amount in dollars.
DifferenceCalculatedCalculated: [Committed in Procore] − [Committed in ERP]
Waiting in stagingAmount ($)Enter the amount in dollars.
UnexplainedCalculatedCalculated: [Difference] − [Waiting in staging]
NoteTextFree text.

See it on real-looking numbers

Constructelligence is a construction intelligence platform: it reads your ERP, project and field systems read-only and does this arithmetic every week, for every job. The demo runs it on a sample eight-job portfolio.

Try the demoJoin the private beta

Frequently asked questions

How does Procore integrate with accounting software?

Through its ERP Integrations tool, a staging area where financial records wait for an accounting approver. Records from the ERP are imported with the ERP's Origin ID; records sent from Procore project tools, such as commitments, are exported to the ERP once approved.

What is an Origin ID in Procore?

The ID of the matching record in the external ERP, stored on the Procore record. Its presence marks a Procore record as synced and lets reports and integrations join Procore and ERP data without matching on names.

Which data syncs from the ERP to Procore?

Typically vendors, jobs and sub jobs, cost codes and cost types, budgets, and payments or job cost. Commitments, commitment change orders and subcontractor invoices usually flow the other way, from Procore to the ERP.

Why does Procore need an accounting approver?

So money only reaches the books after accounting has reviewed it. Exports wait in the ERP Integrations tool until an approver accepts or rejects them; rejected records return to the project tool for editing.

How do I check that Procore and my ERP agree?

Compare committed cost per job in each system monthly. A difference is either a record waiting for approval or a failed sync; anything that isn't waiting in the staging area needs investigating.

CI
Written by the Constructelligence teamConstruction finance and software. Worked examples use the sample demo portfolio; formulas are standard practice. Reviewed September 2026.