The formula
A worked example
On the face of the bids B is lowest at $385,000; once the scope is the same, C is lowest and the spread is $6,000, not $25,000.
How to read it
Record each plug and where its number came from, so the leveling can be checked and the plugs can be bought out or priced when the bidder is awarded.
Why it matters, and where it goes wrong
Subcontractor bids are rarely for the same scope. Leveling shows the true price of each, and records the plugs so they can be closed out when the subcontract is written.
- Taking the lowest raw bid as the lowest price.
- Adding plugs without recording where the numbers came from.
- Forgetting that a bidder's exclusions come back later as change orders.
Go deeper
The full method, with more worked figures, is in the Subcontractor bid leveling: find the real low bid guide.
Related terms
See it on real-looking numbers
Constructelligence calculates this every week for every job, read-only, from your own systems.
Try the demoJoin the private betaFrequently asked questions
What is a plug number in bid leveling?
An estimator's value for a scope item a bidder excluded, added to that bidder's price so it can be compared with the others.
Why level bids?
Because the lowest bid often leaves out scope. Leveling shows the real cost of each bid for the same work.