What is buyout in construction?

Buyout is the process of awarding the subcontracts and purchase orders that the estimate assumed. Buyout savings are the difference between what the estimate carried and what the awards cost.

The formula

Buyout savings = estimated cost of the bought-out scope − awarded cost.

A worked example

Estimate carried for subcontracts$3,200,000
Awarded$3,050,000
Buyout savings = 3,200,000 − 3,050,000$150,000
As a share of the estimate4.7%

Savings can be real or can hide a scope gap that a change order will fill later, so level the bids to the same scope before counting them.

How to read it

Report buyout against the estimate by cost code, and keep the unbought scope visible. A job that is 90% bought out has most of its risk locked in.

Why it matters, and where it goes wrong

Buyout is where much of a job's margin is made or lost. The estimate is a guess; the awards are real prices, and the difference shows up in the forecast immediately.

Go deeper

The full method, with more worked figures, is in the Committed cost in construction: track buyout and the exposure still to buy guide.

See it on real-looking numbers

Constructelligence calculates this every week for every job, read-only, from your own systems.

Try the demoJoin the private beta

Frequently asked questions

What does buyout mean for a general contractor?

Awarding the trade subcontracts and supply orders for the job, ideally for less than the estimate carried.

What is a buyout saving?

The difference between the estimate for a scope and its awarded cost. It is confirmed only once the scope is the same on both sides.