The formula
A worked example
Savings can be real or can hide a scope gap that a change order will fill later, so level the bids to the same scope before counting them.
How to read it
Report buyout against the estimate by cost code, and keep the unbought scope visible. A job that is 90% bought out has most of its risk locked in.
Why it matters, and where it goes wrong
Buyout is where much of a job's margin is made or lost. The estimate is a guess; the awards are real prices, and the difference shows up in the forecast immediately.
- Counting a saving on a subcontract whose scope is not the same as the estimate's.
- Not tracking the unbought scope, so risk is invisible.
- Forgetting that late buyout of long-lead items can cost more than the saving.
Go deeper
The full method, with more worked figures, is in the Committed cost in construction: track buyout and the exposure still to buy guide.
Related terms
See it on real-looking numbers
Constructelligence calculates this every week for every job, read-only, from your own systems.
Try the demoJoin the private betaFrequently asked questions
What does buyout mean for a general contractor?
Awarding the trade subcontracts and supply orders for the job, ideally for less than the estimate carried.
What is a buyout saving?
The difference between the estimate for a scope and its awarded cost. It is confirmed only once the scope is the same on both sides.