The formula
A worked example
A job cost report on paid cost alone shows $150,000 against $420,000. The committed cost shows that $400,000 of the budget is already spoken for.
How to read it
Committed cost plus pending changes is the number that shows exposure. See the committed cost guide for how buyout savings and overruns show up in it.
Why it matters, and where it goes wrong
Cost reports built only on paid cost are always late. Committed cost shows what is already spoken for, so exposure is visible before the invoices arrive.
- Leaving subcontract change orders out of the commitment.
- Entering commitments at a different cost code than the budget.
- Treating uncommitted budget as safe when the remaining scope has not been bought.
Go deeper
The full method, with more worked figures, is in the Committed cost in construction: track buyout and the exposure still to buy guide.
Related terms
See it on real-looking numbers
Constructelligence calculates this every week for every job, read-only, from your own systems.
Try the demoJoin the private betaFrequently asked questions
What is the difference between committed cost and actual cost?
Actual cost is what has been spent or invoiced. Committed cost is everything contracted, including work not yet invoiced.
Why track committed cost?
Because it shows where a job is heading before the invoices arrive. Reports built on actual cost alone are always behind.