What is committed cost in construction?

Committed cost is the total of signed subcontracts, issued purchase orders and approved change orders on a job. It is money the contractor must pay, whether or not it has been invoiced yet.

The formula

Committed cost = subcontracts + purchase orders + approved commitment change orders. Remaining to pay = committed cost − invoiced to date.

A worked example

Concrete budget$420,000
Subcontract$380,000
Approved change order$20,000
Committed cost$400,000
Invoiced to date$150,000
Remaining to pay = 400,000 − 150,000$250,000
Budget not yet committed = 420,000 − 400,000$20,000

A job cost report on paid cost alone shows $150,000 against $420,000. The committed cost shows that $400,000 of the budget is already spoken for.

How to read it

Committed cost plus pending changes is the number that shows exposure. See the committed cost guide for how buyout savings and overruns show up in it.

Why it matters, and where it goes wrong

Cost reports built only on paid cost are always late. Committed cost shows what is already spoken for, so exposure is visible before the invoices arrive.

Go deeper

The full method, with more worked figures, is in the Committed cost in construction: track buyout and the exposure still to buy guide.

See it on real-looking numbers

Constructelligence calculates this every week for every job, read-only, from your own systems.

Try the demoJoin the private beta

Frequently asked questions

What is the difference between committed cost and actual cost?

Actual cost is what has been spent or invoiced. Committed cost is everything contracted, including work not yet invoiced.

Why track committed cost?

Because it shows where a job is heading before the invoices arrive. Reports built on actual cost alone are always behind.