What is a P80 finish date in construction scheduling?

A P80 finish date is the date with an 80% chance of being met or beaten, found by simulating the schedule thousands of times with uncertain durations. A P50 date has even odds.

The formula

Schedule contingency = P80 finish − CPM finish.

A worked example

CPM finishday 200
P50 (even odds)day 214
P80 (four in five)day 236
Contingency = 236 − 20036 days

The CPM date assumes every activity takes its most likely duration, which is why it is usually the optimistic end of the range. The figures here are illustrative.

How to read it

Many owners and lenders ask for the P80 or P90 date. Check that the risks and durations behind it come from real data, not guesses.

Why it matters, and where it goes wrong

A single finish date hides how uncertain it is. The P80 date gives owners and contractors a number they can plan and price contingency against, instead of a date that is likely to be missed.

Go deeper

The full method, with more worked figures, is in the P50, P80 and P90 schedule forecasts: schedule risk analysis and Monte Carlo on a construction schedule, worked through guide.

See it on real-looking numbers

Constructelligence calculates this every week for every job, read-only, from your own systems.

Try the demoJoin the private beta

Frequently asked questions

What is the difference between P50 and P80?

P50 is the date you have a 50% chance of meeting; P80 is the date you have an 80% chance of meeting, so it is later.

Why is the CPM date usually too early?

Activities finish late more often and by more than they finish early, and parallel paths that converge add delay, so the single most-likely date is usually the optimistic one.