The formula
A worked example
The CPM date assumes every activity takes its most likely duration, which is why it is usually the optimistic end of the range. The figures here are illustrative.
How to read it
Many owners and lenders ask for the P80 or P90 date. Check that the risks and durations behind it come from real data, not guesses.
Why it matters, and where it goes wrong
A single finish date hides how uncertain it is. The P80 date gives owners and contractors a number they can plan and price contingency against, instead of a date that is likely to be missed.
- Using optimistic or default durations in the simulation.
- Leaving out risks that apply to many activities at once, such as weather.
- Treating the P80 as a promise instead of a probability.
Go deeper
The full method, with more worked figures, is in the P50, P80 and P90 schedule forecasts: schedule risk analysis and Monte Carlo on a construction schedule, worked through guide.
Related terms
See it on real-looking numbers
Constructelligence calculates this every week for every job, read-only, from your own systems.
Try the demoJoin the private betaFrequently asked questions
What is the difference between P50 and P80?
P50 is the date you have a 50% chance of meeting; P80 is the date you have an 80% chance of meeting, so it is later.
Why is the CPM date usually too early?
Activities finish late more often and by more than they finish early, and parallel paths that converge add delay, so the single most-likely date is usually the optimistic one.