What is total float in construction scheduling?

Total float is how long an activity can slip without delaying the project finish. Activities with zero total float are on the critical path.

The formula

Total float = late start − early start (or late finish − early finish).

A worked example

Underground MEP: early startday 15
Underground MEP: late startday 17
Total float = 17 − 152 days
A 3-day slip moves the finish by3 − 2 = 1 day

The first two days of delay are absorbed by the float; from the third day the finish moves day for day.

How to read it

Float belongs to the project, not to whichever trade reaches it first. Very large float usually means missing logic, not spare time.

Why it matters, and where it goes wrong

Float tells you which activities can absorb a delay and which cannot, and it is the basis for every claim about who delayed a job. It is only reliable when the schedule's logic is.

Go deeper

The full method, with more worked figures, is in the The critical path method in construction, worked through one schedule guide. To run it on your own numbers, use the schedule health check.

See it on real-looking numbers

Constructelligence calculates this every week for every job, read-only, from your own systems.

Try the demoJoin the private beta

Frequently asked questions

What is the difference between total float and free float?

Total float is the delay an activity can take without delaying the project finish. Free float is the delay it can take without delaying the early start of its successors.

What does negative float mean?

The schedule cannot meet a required date: the activities on that path need more time than is available.