The formula
A worked example
The first two days of delay are absorbed by the float; from the third day the finish moves day for day.
How to read it
Float belongs to the project, not to whichever trade reaches it first. Very large float usually means missing logic, not spare time.
Why it matters, and where it goes wrong
Float tells you which activities can absorb a delay and which cannot, and it is the basis for every claim about who delayed a job. It is only reliable when the schedule's logic is.
- Trusting float on a schedule with open ends or hard constraints.
- Letting one trade use the float that the whole project needs.
- Ignoring negative float because the finish date still looks achievable.
Go deeper
The full method, with more worked figures, is in the The critical path method in construction, worked through one schedule guide. To run it on your own numbers, use the schedule health check.
Related terms
See it on real-looking numbers
Constructelligence calculates this every week for every job, read-only, from your own systems.
Try the demoJoin the private betaFrequently asked questions
What is the difference between total float and free float?
Total float is the delay an activity can take without delaying the project finish. Free float is the delay it can take without delaying the early start of its successors.
What does negative float mean?
The schedule cannot meet a required date: the activities on that path need more time than is available.