The formula
A worked example
The chain A–B–C–E–F–G–I is 59 days, so the project finishes on day 59. Underground MEP and MEP rough-in have float and are not on it.
How to read it
The critical path can change during a job: when a non-critical activity slips by more than its float, it becomes critical.
Why it matters, and where it goes wrong
The critical path tells a manager which activities to protect and which to leave alone. Resources put on a non-critical activity do not move the finish date.
- Assuming the critical path stays the same through the job.
- Reading it off a schedule whose logic has not been checked.
- Forgetting that near-critical paths can become critical after small slips.
Go deeper
The full method, with more worked figures, is in the The critical path method in construction, worked through one schedule guide. To run it on your own numbers, use the schedule health check.
Related terms
See it on real-looking numbers
Constructelligence calculates this every week for every job, read-only, from your own systems.
Try the demoJoin the private betaFrequently asked questions
How do you find the critical path?
Run a forward and backward pass over the schedule logic; activities with zero total float form the critical path.
Can a project have more than one critical path?
Yes. Several chains can have zero float, and a delay on any of them moves the finish.