The formula
A worked example
The $80,000 held is earned money the contractor does not have yet. On a long job it is a large part of working capital, and a subcontractor's retainage often waits for the whole job to finish.
How to read it
Check that the rate, any reduction (for example at 50% complete) and the release terms in each subcontract match the prime contract, or the GC can end up holding more than it is held.
Why it matters, and where it goes wrong
Retainage ties up money that has been earned, often for months after the work is done, so it affects cash flow, the WIP schedule and what a subcontractor can bid. It is also a frequent source of disputes at closeout.
- Not matching the subcontract's rate and release terms to the prime contract.
- Forgetting to ask for a reduction at the milestone the contract allows.
- Leaving retainage uncollected after substantial completion because nobody tracked it.
Go deeper
The full method, with more worked figures, is in the Retainage in construction: how it works and how to get it back guide. To run it on your own numbers, use the pay application and retainage calculator.
Related terms
See it on real-looking numbers
Constructelligence calculates this every week for every job, read-only, from your own systems.
Try the demoJoin the private betaFrequently asked questions
How is retainage calculated?
Multiply the work completed and stored to date by the retainage rate. At 10% on $800,000 of completed work, $80,000 is held.
When is retainage released?
According to the contract: often at substantial completion or after final completion and acceptance. Some contracts reduce the rate at a milestone such as 50% complete. Check the terms and the law for your state.