What is over-billing in construction?

Over-billing means billing the owner more than the revenue earned to date. The contractor has been paid for work not yet done, which shows as a liability on the WIP schedule.

The formula

Over-billing = billings to date − earned revenue. Earned revenue = contract × (cost to date ÷ estimated total cost).

A worked example

Contract$2,000,000
Cost to date · estimated total cost$900,000 · $1,800,000
Percent complete = 900,000 ÷ 1,800,00050%
Earned revenue$1,000,000
Billed to date$1,150,000
Over-billing = 1,150,000 − 1,000,000$150,000

The job is over-billed by $150,000: cash is ahead of the work, which looks good until the cost to finish arrives.

How to read it

Over-billing is a liability, not profit. A contractor with large over-billings on every job can run short of cash when the jobs wind down and the billings stop.

Why it matters, and where it goes wrong

Over-billing is a liability on the balance sheet, so it affects bonding capacity and the view a lender takes of the company. It also says something about the next few months of cash.

Go deeper

The full method, with more worked figures, is in the The WIP schedule: over-billing, under-billing and why they matter guide. To run it on your own numbers, use the over/under billing calculator.

See it on real-looking numbers

Constructelligence calculates this every week for every job, read-only, from your own systems.

Try the demoJoin the private beta

Frequently asked questions

Is over-billing bad?

It is not a fault in itself, but it is a liability: the cash collected has to be earned by the work still to do. Large over-billings that are not backed by cash can hide a loss.

How do you calculate over-billing?

Billings to date minus earned revenue, where earned revenue is the contract times the cost-to-cost percent complete.