The formula
A worked example
The job is over-billed by $150,000: cash is ahead of the work, which looks good until the cost to finish arrives.
How to read it
Over-billing is a liability, not profit. A contractor with large over-billings on every job can run short of cash when the jobs wind down and the billings stop.
Why it matters, and where it goes wrong
Over-billing is a liability on the balance sheet, so it affects bonding capacity and the view a lender takes of the company. It also says something about the next few months of cash.
- Counting over-billed cash as profit.
- Not noticing that over-billing is shrinking as jobs wind down.
- Forecasting cost at completion too low, which understates percent complete and overstates over-billing.
Go deeper
The full method, with more worked figures, is in the The WIP schedule: over-billing, under-billing and why they matter guide. To run it on your own numbers, use the over/under billing calculator.
Related terms
See it on real-looking numbers
Constructelligence calculates this every week for every job, read-only, from your own systems.
Try the demoJoin the private betaFrequently asked questions
Is over-billing bad?
It is not a fault in itself, but it is a liability: the cash collected has to be earned by the work still to do. Large over-billings that are not backed by cash can hide a loss.
How do you calculate over-billing?
Billings to date minus earned revenue, where earned revenue is the contract times the cost-to-cost percent complete.