The formula
A worked example
If the structure is 50% complete, the line bills $100,000. The owner or architect checks each percentage against the work in place.
How to read it
Lines should match how the job is built and how it will be tracked. Lines that are too coarse hide progress; lines that are front-loaded are the first thing an owner questions.
Why it matters, and where it goes wrong
The schedule of values decides how fast the contractor is paid and how the owner can check each pay application. It is set once at the start and used for every bill after, so mistakes in it follow the whole job.
- Using lines too coarse to show progress, so every month is a negotiation.
- Front-loading early lines, which owners and architects will reject.
- Not adding approved change orders as their own lines.
Go deeper
The full method, with more worked figures, is in the Schedule of values in construction: a worked example, how to build one and how to avoid front-loading guide. To run it on your own numbers, use the pay application and retainage calculator.
Related terms
See it on real-looking numbers
Constructelligence calculates this every week for every job, read-only, from your own systems.
Try the demoJoin the private betaFrequently asked questions
What is a schedule of values used for?
To bill progress payments. Each month the contractor claims a percentage of each line, and the owner checks the percentages against the work in place.
What is the difference between a schedule of values and a G703?
The schedule of values is the breakdown of the contract sum. The AIA G703 is the form on which it is laid out and billed against each month.