Retaining wall calculator: blocks, caps and gravel
Plan a segmental block retaining wall. Enter the length, the height above grade and the block size, and get the courses, the blocks and caps to order, the base gravel, the drainage backfill and the block cost.
Retaining wall: blocks, caps & gravel
Enter the wall length and height and the block size, and get the courses, the blocks and caps to order, the base gravel, the drainage backfill and the block cost.
The wall
Result
Courses = height × 12 ÷ block height, rounded up. Blocks = courses × blocks per course × (1 + waste), where blocks per course = length × 12 ÷ block length. Caps = blocks per course. Base gravel = length × trench width × depth ÷ 27 (cubic yards); backfill = length × height × backfill width ÷ 27.
How to use it
- Enter the wall length and the height above grade.
- Enter the block length and height.
- Set waste and the base trench and backfill sizes.
- Enter the price per block and read the blocks, caps, gravel and cost.
A worked example
What a block wall needs besides blocks
- A buried first course. The base course is set below grade on a compacted gravel base, commonly one course or at least 6 in deep.
- Drainage. Gravel backfill behind the wall, a perforated drain pipe at the base and filter fabric to keep soil out; water pressure behind the wall is what makes walls fail.
- Geogrid. Taller walls use layers of geogrid tied into the blocks and extended into the backfill.
- Engineering. Many jurisdictions require a permit or an engineer's design for walls over about 4 ft, or where there is a surcharge such as a slope, driveway or building above.
What the calculator leaves out
Geogrid, drain pipe, filter fabric, adhesive for caps, and excavation and haul-off of the soil. Those belong in the estimate on their own lines.
Questions
How do you calculate retaining wall blocks?
Divide the wall height by the block height for the courses, divide the length by the block length for blocks per course, and multiply. Add waste and a row of caps.
How much gravel do I need behind a retaining wall?
Length × height × the backfill width, divided by 27 for cubic yards, plus the base. A 12 in wide drainage zone on a 30 × 4 ft wall is about 4.4 cubic yards.
How high can a retaining wall be without a permit?
It varies by place. Many jurisdictions require a permit or an engineer above about 4 ft, or when the wall carries a slope or a structure, so check with your building department.
How deep should the base be?
A compacted gravel base commonly at least 6 in deep, with the first course buried; follow the block maker's instructions and any engineered design.