What is an allowance in a construction contract?

An allowance is a budget amount in a contract for an item the owner has not yet chosen, such as tile or light fixtures. When the final choice costs more or less, the contract price is adjusted by the difference.

The formula

Contract adjustment = actual cost of the selection − allowance (plus markup, as the contract states).

A worked example

Tile allowance, including installation$8,000
Tile chosen, with installation$9,300
Overage = 9,300 − 8,000$1,300
Change order, with 15% markup on the overage$1,495

The overage becomes a change order. If the choice comes in below the allowance the owner receives a credit.

How to read it

Write down what each allowance includes (material only, or installed), or the overage becomes a dispute.

Why it matters, and where it goes wrong

Allowances let a contract be signed before every choice is made, but they move the cost risk to the buyer, and unclear allowances are a common cause of disputes on remodels and homes.

Go deeper

The full method, with more worked figures, is in the Home builder software: what to run, what to track, and where jobs lose money guide.

See it on real-looking numbers

Constructelligence calculates this every week for every job, read-only, from your own systems.

Try the demoJoin the private beta

Frequently asked questions

What happens if a selection costs more than the allowance?

The contract sum increases by the difference, usually through a change order with the markup the contract states.

What should an allowance include?

The contract should say whether it covers material only or material, delivery and installation, and any tax.