The formula
A worked example
The overage becomes a change order. If the choice comes in below the allowance the owner receives a credit.
How to read it
Write down what each allowance includes (material only, or installed), or the overage becomes a dispute.
Why it matters, and where it goes wrong
Allowances let a contract be signed before every choice is made, but they move the cost risk to the buyer, and unclear allowances are a common cause of disputes on remodels and homes.
- Not stating whether the allowance includes installation and tax.
- Setting the allowance below the realistic cost to win the job.
- Not tracking each selection against its allowance as the choices are made.
Go deeper
The full method, with more worked figures, is in the Home builder software: what to run, what to track, and where jobs lose money guide.
Related terms
See it on real-looking numbers
Constructelligence calculates this every week for every job, read-only, from your own systems.
Try the demoJoin the private betaFrequently asked questions
What happens if a selection costs more than the allowance?
The contract sum increases by the difference, usually through a change order with the markup the contract states.
What should an allowance include?
The contract should say whether it covers material only or material, delivery and installation, and any tax.