Constructelligence
Glossary · billing

What is a change order in construction?

A change order is a signed amendment to the contract that changes the contract sum, the time, or both. Work done before it is signed is unapproved and at the contractor's risk.

The formula

Revised contract sum = original contract sum + approved change orders.

A worked example

Original contract sum$4,000,000
Change order 1: added scope+$85,000
Change order 2: deleted scope−$20,000
Revised contract sum$4,065,000

Each approved change order also changes the schedule of values and the billing, so the next pay application includes it as its own line.

How to read it

Track the unsigned amount separately: cost on a change that has not been approved is exposure, not revenue.

Why it matters, and where it goes wrong

Change orders move the contract sum, the schedule of values and the billing. Work done without one is at the contractor's risk, which is why tracking unsigned change work separately matters.

Go deeper

The full method, with more worked figures, is in the Change order management: stop carrying work nobody has signed for guide. To run it on your own numbers, use the change order pricing calculator.

See it on real-looking numbers

Constructelligence calculates this every week for every job, read-only, from your own systems.

Try the demoJoin the private beta

Frequently asked questions

What is the difference between a change order and a change order request?

A request is a priced proposal sent to the owner. A change order is the signed agreement that changes the contract.

What happens if work starts before the change order is signed?

The cost is booked against an unapproved change, and the contractor carries the risk that it will not be approved or paid in full.