What is time and materials (T&M) in construction?

Time and materials billing charges for the actual labor hours at agreed rates plus materials at cost with an agreed markup. It is used when the scope cannot be priced in advance.

The formula

T&M bill = labor hours × agreed rate + materials × (1 + markup) + any equipment.

A worked example

Labor: 120 hours × $68$8,160
Materials at cost$3,450
Markup on materials, 10%$345
T&M bill = 8,160 + 3,450 + 345$11,955

The contract states the rates and the markup, and the signed daily tickets are the support for each hour and each item.

How to read it

T&M shifts the cost risk to the owner, so owners often ask for a not-to-exceed cap and approval of the tickets each day.

Why it matters, and where it goes wrong

T&M is a common way to pay for work whose scope is unclear, but without discipline it becomes a source of disputes. The agreement and the tickets are what hold up the bill.

Go deeper

The full method, with more worked figures, is in the Construction invoice template: what to put on it, a filled-in example, and a free download guide. To run it on your own numbers, use the change order pricing calculator.

See it on real-looking numbers

Constructelligence calculates this every week for every job, read-only, from your own systems.

Try the demoJoin the private beta

Frequently asked questions

What is a not-to-exceed T&M?

A time and materials agreement with a cap. The contractor bills actual time and materials but cannot exceed the cap without approval.

What support does a T&M invoice need?

Signed daily tickets for the labor, equipment and materials, at the rates in the contract.