The formula
A worked example
At the current annual revenue the backlog says how many months of work are secured, which is the figure lenders and sureties ask about.
How to read it
Backlog quality matters as much as size: a large backlog of low-margin or faded jobs is worth less than a smaller one of healthy work.
Why it matters, and where it goes wrong
Backlog is how a contractor, a lender or a surety judges how much future revenue is secured. Its quality, the margin and risk in it, matters as much as its size.
- Counting work that is awarded but not contracted.
- Leaving out approved changes in the contract value.
- Reporting size without margin, so a backlog full of faded jobs looks healthy.
Go deeper
The full method, with more worked figures, is in the Construction KPIs: the 12 financial metrics that actually matter guide.
Related terms
See it on real-looking numbers
Constructelligence calculates this every week for every job, read-only, from your own systems.
Try the demoJoin the private betaFrequently asked questions
How do you calculate backlog?
For each open job, subtract the earned revenue to date from the contract value (including approved change orders), and add them up.
What is the difference between backlog and pipeline?
Backlog is work under contract. Pipeline is work being bid or negotiated that is not yet awarded.