What is backlog in construction?

Backlog is contracted work not yet performed: the contract value less the revenue earned to date, summed over all open jobs. It shows how much work is already secured.

The formula

Backlog = contract value − earned revenue to date, summed over open jobs.

A worked example

Job A: $2,000,000 contract, $1,000,000 earned$1,000,000
Job B: $1,200,000 contract, $900,000 earned$300,000
Job C: $5,000,000 contract, $1,500,000 earned$3,500,000
Backlog$4,800,000

At the current annual revenue the backlog says how many months of work are secured, which is the figure lenders and sureties ask about.

How to read it

Backlog quality matters as much as size: a large backlog of low-margin or faded jobs is worth less than a smaller one of healthy work.

Why it matters, and where it goes wrong

Backlog is how a contractor, a lender or a surety judges how much future revenue is secured. Its quality, the margin and risk in it, matters as much as its size.

Go deeper

The full method, with more worked figures, is in the Construction KPIs: the 12 financial metrics that actually matter guide.

See it on real-looking numbers

Constructelligence calculates this every week for every job, read-only, from your own systems.

Try the demoJoin the private beta

Frequently asked questions

How do you calculate backlog?

For each open job, subtract the earned revenue to date from the contract value (including approved change orders), and add them up.

What is the difference between backlog and pipeline?

Backlog is work under contract. Pipeline is work being bid or negotiated that is not yet awarded.