What is fade in construction?

Fade is the drop in a job's forecast gross margin since award. A job awarded at a 12% margin and now forecast at 8% has faded four points.

The formula

Fade = gross margin at award − current forecast gross margin.

A worked example

Contract$2,000,000
Margin at award: 12%, profit$240,000
Forecast cost now (EAC)$1,840,000
Forecast gross profit = 2,000,000 − 1,840,000$160,000 (8%)
Fade = 12% − 8%4 points ($80,000)

Fade is the number that shows where margin is being lost between award and completion.

How to read it

Look at fade across all jobs. A company where most jobs fade is bidding too tight or forecasting too late; a few jobs that fade a lot point to specific problems.

Why it matters, and where it goes wrong

Fade makes margin loss visible before it reaches the final job cost report. A portfolio where most jobs fade points at the estimating, the buyout or the forecasting process rather than at one job.

Go deeper

The full method, with more worked figures, is in the Construction KPIs: the 12 financial metrics that actually matter guide. To run it on your own numbers, use the cost overrun and EAC calculator.

See it on real-looking numbers

Constructelligence calculates this every week for every job, read-only, from your own systems.

Try the demoJoin the private beta

Frequently asked questions

What causes fade in construction?

Cost growth against the estimate, unpriced changes, lost productivity, and buyout that comes in above the estimate.

How is fade different from VAC?

VAC is the dollar difference between budget and forecast cost. Fade is the change in margin, usually in percentage points, since award.