The formula
A worked example
Fade is the number that shows where margin is being lost between award and completion.
How to read it
Look at fade across all jobs. A company where most jobs fade is bidding too tight or forecasting too late; a few jobs that fade a lot point to specific problems.
Why it matters, and where it goes wrong
Fade makes margin loss visible before it reaches the final job cost report. A portfolio where most jobs fade points at the estimating, the buyout or the forecasting process rather than at one job.
- Comparing margin at completion with a margin that was never recorded at award.
- Excluding approved changes from the award margin.
- Looking at fade only on finished jobs, when it is most useful on open ones.
Go deeper
The full method, with more worked figures, is in the Construction KPIs: the 12 financial metrics that actually matter guide. To run it on your own numbers, use the cost overrun and EAC calculator.
Related terms
See it on real-looking numbers
Constructelligence calculates this every week for every job, read-only, from your own systems.
Try the demoJoin the private betaFrequently asked questions
What causes fade in construction?
Cost growth against the estimate, unpriced changes, lost productivity, and buyout that comes in above the estimate.
How is fade different from VAC?
VAC is the dollar difference between budget and forecast cost. Fade is the change in margin, usually in percentage points, since award.