Constructelligence
Glossary · WIP

What is a WIP schedule in construction?

A WIP schedule is the report of every open job showing contract value, forecast cost, percent complete, earned revenue, billings, and the resulting over- or under-billing. Sureties, lenders and owners use it to judge a contractor's health.

The formula

Percent complete = cost to date ÷ estimated total cost. Earned revenue = contract × percent complete. Over/under = billings − earned revenue.

A worked example

JobContractEst. costCost to date% completeEarned revenueBilledOver / (under)
A$2,000,000$1,800,000$900,00050%$1,000,000$1,150,000$150,000
B$1,200,000$1,000,000$750,00075%$900,000$840,000($60,000)
Total$3,200,000$2,800,000$1,650,000$1,900,000$1,990,000$90,000

The company is net over-billed by $90,000: $150,000 over on job A less $60,000 under on job B.

How to read it

The forecast cost in each row is the number to challenge. A WIP schedule is only as good as the estimates to complete behind it.

Why it matters, and where it goes wrong

The WIP schedule is the document sureties and banks use to judge a contractor, and it is the best monthly summary of the company's real position. Its quality depends on each project manager's forecast.

Go deeper

The full method, with more worked figures, is in the The WIP schedule: over-billing, under-billing and why they matter guide. To run it on your own numbers, use the over/under billing calculator.

See it on real-looking numbers

Constructelligence calculates this every week for every job, read-only, from your own systems.

Try the demoJoin the private beta

Frequently asked questions

What is a WIP schedule used for?

To report each open job's earned revenue and its over- or under-billing, so management, sureties, banks and auditors can see the real position.

How often should a WIP schedule be updated?

Monthly, with fresh estimates to complete from each project manager, since the percent complete depends on them.