The formula
A worked example
| Job | Contract | Est. cost | Cost to date | % complete | Earned revenue | Billed | Over / (under) |
|---|---|---|---|---|---|---|---|
| A | $2,000,000 | $1,800,000 | $900,000 | 50% | $1,000,000 | $1,150,000 | $150,000 |
| B | $1,200,000 | $1,000,000 | $750,000 | 75% | $900,000 | $840,000 | ($60,000) |
| Total | $3,200,000 | $2,800,000 | $1,650,000 | $1,900,000 | $1,990,000 | $90,000 |
The company is net over-billed by $90,000: $150,000 over on job A less $60,000 under on job B.
How to read it
The forecast cost in each row is the number to challenge. A WIP schedule is only as good as the estimates to complete behind it.
Why it matters, and where it goes wrong
The WIP schedule is the document sureties and banks use to judge a contractor, and it is the best monthly summary of the company's real position. Its quality depends on each project manager's forecast.
- Using stale estimates to complete, so earned revenue is wrong.
- Leaving out jobs with losses, which should be recognised in full when they are known.
- Not reconciling the schedule to the general ledger each month.
Go deeper
The full method, with more worked figures, is in the The WIP schedule: over-billing, under-billing and why they matter guide. To run it on your own numbers, use the over/under billing calculator.
Related terms
See it on real-looking numbers
Constructelligence calculates this every week for every job, read-only, from your own systems.
Try the demoJoin the private betaFrequently asked questions
What is a WIP schedule used for?
To report each open job's earned revenue and its over- or under-billing, so management, sureties, banks and auditors can see the real position.
How often should a WIP schedule be updated?
Monthly, with fresh estimates to complete from each project manager, since the percent complete depends on them.