The formula
A worked example
The same job at 60% complete has earned value of $600,000, so CPI is 600,000 ÷ 620,000 = 0.968. If that efficiency continues, EAC = 1,000,000 ÷ 0.968 = $1,033,333. The two methods bracket the likely outcome; a gap between them is a reason to look at the remaining work.
How to read it
Compare the EAC with the budget every month, by cost code. A forecast that never moves from the budget is usually a forecast nobody has updated.
Why it matters, and where it goes wrong
EAC is the number a surety, a lender and the owner's auditor all ask for, because it turns a job from "how much have we spent" into "how much will we have spent". A job that looks fine on cost to date can still finish well over budget.
- Taking budget minus cost to date and calling it the estimate to complete.
- Updating the forecast only when a number is requested, not every month.
- Holding the forecast at budget until the job is nearly finished, which hides a loss until it is too late to act.
Go deeper
The full method, with more worked figures, is in the Job cost forecasting: how to forecast a job’s cost at completion guide. To run it on your own numbers, use the cost overrun and EAC calculator.
Related terms
See it on real-looking numbers
Constructelligence calculates this every week for every job, read-only, from your own systems.
Try the demoJoin the private betaFrequently asked questions
How do you calculate EAC in construction?
Add the actual cost to date to the estimate to complete. If current efficiency will continue, divide the budget at completion by the cost performance index instead.
What is the difference between EAC and ETC?
EAC is the forecast total cost of the job; ETC is the forecast cost of the work that remains. EAC equals cost to date plus ETC.