What is the DART rate in construction safety?

DART stands for days away, restricted or transferred. The DART rate counts the cases that led to lost days, restricted work or job transfer, per 100 workers, on the 200,000-hour basis.

The formula

DART rate = DART cases × 200,000 ÷ hours worked.

A worked example

DART cases2
Hours worked400,000
DART rate = 2 × 200,000 ÷ 400,0001.0

Where TRIR counts every recordable case, DART counts only the more serious ones that took someone off normal duty.

How to read it

A gap between TRIR and DART is normal; a company with many recordables and almost no DART cases may be managing severity well. Owners that set a DART limit in prequalification usually state it on the same 200,000-hour basis, so check that your hours and case counts are calculated the same way before comparing.

Why it matters, and where it goes wrong

DART separates severity from frequency. Two companies with the same TRIR can have very different DART rates, and the second one shows how serious the injuries are.

Go deeper

The full method, with more worked figures, is in the Construction safety metrics: TRIR, DART, LTIR and EMR, calculated guide. To run it on your own numbers, use the TRIR and DART calculator.

See it on real-looking numbers

Constructelligence calculates this every week for every job, read-only, from your own systems.

Try the demoJoin the private beta

Frequently asked questions

What is the difference between TRIR and DART?

TRIR counts all recordable cases; DART counts only cases with days away from work, restricted duty or job transfer.

How do you calculate the DART rate?

Multiply DART cases by 200,000 and divide by hours worked.