The formula
A worked example
200,000 hours is 100 workers for a year at 2,000 hours each, so a TRIR of 2.0 means 2 recordable cases per 100 workers per year.
How to read it
Owners use TRIR to prequalify contractors, often with a limit. A small company's TRIR swings widely with one case, so look at it over several years.
Why it matters, and where it goes wrong
TRIR is used by owners to prequalify contractors and by insurers to price risk, so it affects whether a contractor can bid on a job at all.
- Using the wrong hours, for example leaving out subcontractor or overtime hours.
- Judging a small company on one year when a single case swings the rate widely.
- Comparing TRIR across companies that classify cases differently.
Go deeper
The full method, with more worked figures, is in the Construction safety metrics: TRIR, DART, LTIR and EMR, calculated guide. To run it on your own numbers, use the TRIR and DART calculator.
Related terms
See it on real-looking numbers
Constructelligence calculates this every week for every job, read-only, from your own systems.
Try the demoJoin the private betaFrequently asked questions
How do you calculate TRIR?
Multiply recordable cases by 200,000 and divide by hours worked.
Why 200,000 hours?
It is 100 full-time workers working 40 hours a week for 50 weeks, so the rate reads as cases per 100 workers.