What is ETC (estimate to complete) in construction?

Estimate to complete is the forecast cost of the work that remains on a job. Added to the cost already spent, it gives the estimate at completion.

The formula

ETC = estimate at completion − actual cost to date. Bottom-up: ETC = the cost of each remaining quantity of work.

A worked example

Remaining labor: 3,200 hours × $62$198,400
Remaining material$150,000
Remaining subcontracts$80,000
ETC$428,400
Actual cost to date$620,000
EAC = 620,000 + 428,400$1,048,400

A bottom-up ETC counts what is left, line by line. It is more work than taking the budget less cost to date, and it is the version that catches a job that is running out of money before it runs out of work.

How to read it

Budget minus cost to date is not an ETC. It assumes the rest of the job will cost exactly what was estimated, whatever has happened so far.

Why it matters, and where it goes wrong

Estimate to complete is where project managers' judgment goes into the numbers. Every later figure, the EAC, the variance, the percent complete on the WIP schedule, depends on it.

Go deeper

The full method, with more worked figures, is in the Job cost forecasting: how to forecast a job’s cost at completion guide. To run it on your own numbers, use the cost overrun and EAC calculator.

See it on real-looking numbers

Constructelligence calculates this every week for every job, read-only, from your own systems.

Try the demoJoin the private beta

Frequently asked questions

How do you calculate estimate to complete?

Price the remaining work line by line (quantities, labor hours and rates, material and subcontracts), or subtract the cost to date from a revised estimate at completion.

Is ETC the same as remaining budget?

No. Remaining budget is the original budget less cost to date. ETC is a fresh forecast of what the remaining work will cost, which may be more or less.