Glossary · earned value

What is CPI (cost performance index) in construction?

Cost performance index is earned value divided by actual cost. It shows how much work each dollar spent has bought: below 1.0 the job is over budget for the work done, above 1.0 it is under.

The formula

CPI = earned value (EV) ÷ actual cost (AC).

A worked example

Earned value: 60% of a $1,000,000 budget$600,000
Actual cost to date$620,000
CPI = 600,000 ÷ 620,0000.968

Each dollar spent has bought about 97 cents of budgeted work, so the job is running about 3.2% over for the work completed.

How to read it

CPI is a rate, not a forecast on its own. Early in a job it is noisy; later, a CPI that has been steady for months is a good predictor of where cost will end up.

Why it matters, and where it goes wrong

CPI turns cost performance into one comparable number across jobs of any size, so a controller can rank a portfolio and look first at the worst. It also feeds the forecast: a steady CPI is a basis for the estimate at completion.

Go deeper

The full method, with more worked figures, is in the Earned value management for construction, explained with one job guide.

See it on real-looking numbers

Constructelligence calculates this every week for every job, read-only, from your own systems.

Try the demoJoin the private beta

Frequently asked questions

What is a good CPI?

1.0 or above means the work done has cost no more than budgeted. Below 1.0 the job is over budget for the work completed.

How is CPI different from SPI?

CPI measures cost efficiency (earned value against actual cost); SPI measures schedule efficiency (earned value against planned value).