The formula
A worked example
The job is forecast to finish $50,000 over budget, which comes straight out of the margin.
How to read it
Track VAC by cost code as well as for the whole job: a small total can hide one code that is far over, paid for by another that is not yet complete.
Why it matters, and where it goes wrong
A negative variance at completion is an early warning with a dollar figure on it. Used monthly, it shows whether a job is recovering or sliding while there is still time to change the outcome.
- Reading it only for the whole job and missing the cost codes that are far over.
- Netting an overrun against a saving that has not been bought out.
- Treating a small variance as safe when the forecast behind it has not been updated.
Go deeper
The full method, with more worked figures, is in the Job cost forecasting: how to forecast a job’s cost at completion guide. To run it on your own numbers, use the cost overrun and EAC calculator.
Related terms
See it on real-looking numbers
Constructelligence calculates this every week for every job, read-only, from your own systems.
Try the demoJoin the private betaFrequently asked questions
What does a negative VAC mean?
The forecast cost exceeds the budget, so the job is forecast to finish over budget by that amount.
What is the difference between VAC and fade?
VAC compares forecast cost with budget in dollars. Fade compares the forecast gross margin with the margin at award, usually in percentage points.