What is variance at completion (VAC) in construction?

Variance at completion is the difference between the budget and the forecast total cost: positive means the job is forecast to finish under budget, negative means over.

The formula

VAC = budget at completion (BAC) − estimate at completion (EAC).

A worked example

Budget at completion$1,000,000
Estimate at completion$1,050,000
VAC = 1,000,000 − 1,050,000−$50,000
As a share of budget−5.0%

The job is forecast to finish $50,000 over budget, which comes straight out of the margin.

How to read it

Track VAC by cost code as well as for the whole job: a small total can hide one code that is far over, paid for by another that is not yet complete.

Why it matters, and where it goes wrong

A negative variance at completion is an early warning with a dollar figure on it. Used monthly, it shows whether a job is recovering or sliding while there is still time to change the outcome.

Go deeper

The full method, with more worked figures, is in the Job cost forecasting: how to forecast a job’s cost at completion guide. To run it on your own numbers, use the cost overrun and EAC calculator.

See it on real-looking numbers

Constructelligence calculates this every week for every job, read-only, from your own systems.

Try the demoJoin the private beta

Frequently asked questions

What does a negative VAC mean?

The forecast cost exceeds the budget, so the job is forecast to finish over budget by that amount.

What is the difference between VAC and fade?

VAC compares forecast cost with budget in dollars. Fade compares the forecast gross margin with the margin at award, usually in percentage points.