The formula
A worked example
The crew is using 15% more hours than the estimate allowed, so the remaining labor should be forecast at 15% over unless something changes.
How to read it
Compute it weekly by cost code; averaged over a whole job it hides the codes that are running badly.
Why it matters, and where it goes wrong
The productivity factor shows how a crew is performing against the estimate, by cost code, while there is still time to change the forecast or the way the work is done.
- Averaging over the whole job, which hides the codes that are running badly.
- Using hours charged to a code that includes other work.
- Forecasting the rest of the job at the estimated rate when the factor has been consistently high.
Go deeper
The full method, with more worked figures, is in the Construction labor forecasting: from burn rate to machine learning guide.
Related terms
See it on real-looking numbers
Constructelligence calculates this every week for every job, read-only, from your own systems.
Try the demoJoin the private betaFrequently asked questions
How do you calculate labor productivity in construction?
Divide actual hours by earned hours, where earned hours are the installed quantity times the estimated hours per unit.
What does a productivity factor of 1.2 mean?
Crews are using 20% more hours than the estimate allowed for the work installed.