What is a productivity factor in construction?

The productivity factor is actual hours divided by earned hours. Above 1.0 crews have used more hours than the estimate allowed for the work installed.

The formula

Productivity factor = actual hours ÷ earned hours. Earned hours = installed quantity × estimated hours per unit.

A worked example

Installed: 4,000 LF × 0.25 h per LF1,000 earned hours
Actual hours charged1,150
Productivity factor = 1,150 ÷ 1,0001.15
Extra hours at $75 an hour = 150 × 75$11,250

The crew is using 15% more hours than the estimate allowed, so the remaining labor should be forecast at 15% over unless something changes.

How to read it

Compute it weekly by cost code; averaged over a whole job it hides the codes that are running badly.

Why it matters, and where it goes wrong

The productivity factor shows how a crew is performing against the estimate, by cost code, while there is still time to change the forecast or the way the work is done.

Go deeper

The full method, with more worked figures, is in the Construction labor forecasting: from burn rate to machine learning guide.

See it on real-looking numbers

Constructelligence calculates this every week for every job, read-only, from your own systems.

Try the demoJoin the private beta

Frequently asked questions

How do you calculate labor productivity in construction?

Divide actual hours by earned hours, where earned hours are the installed quantity times the estimated hours per unit.

What does a productivity factor of 1.2 mean?

Crews are using 20% more hours than the estimate allowed for the work installed.