What is under-billing in construction?

Under-billing means earned revenue exceeds what has been billed to the owner. The contractor is financing the work, and the difference is an asset on the WIP schedule.

The formula

Under-billing = earned revenue − billings to date.

A worked example

Earned revenue (50% of $2,000,000)$1,000,000
Billed to date$880,000
Under-billing = 1,000,000 − 880,000$120,000

The contractor has done $120,000 of work it has not yet billed for. It is real money only if the owner accepts the work and the contract allows the billing.

How to read it

Persistent under-billing is a cash problem and sometimes a sign of weak billing discipline or a schedule of values that does not match the work.

Why it matters, and where it goes wrong

Under-billing is work done and not yet billed, so it is cash the contractor is financing. Left alone it grows, and a surety reading the WIP schedule will ask why.

Go deeper

The full method, with more worked figures, is in the The WIP schedule: over-billing, under-billing and why they matter guide. To run it on your own numbers, use the over/under billing calculator.

See it on real-looking numbers

Constructelligence calculates this every week for every job, read-only, from your own systems.

Try the demoJoin the private beta

Frequently asked questions

What causes under-billing?

Billing less than the work done: late or missing pay applications, a schedule of values that does not match the work, stored materials not billed, or unapproved change work.

Is under-billing an asset?

Yes, it appears on the WIP schedule as an underbilling asset, but it only converts to cash when it is billed and paid.