The formula
A worked example
The contractor has done $120,000 of work it has not yet billed for. It is real money only if the owner accepts the work and the contract allows the billing.
How to read it
Persistent under-billing is a cash problem and sometimes a sign of weak billing discipline or a schedule of values that does not match the work.
Why it matters, and where it goes wrong
Under-billing is work done and not yet billed, so it is cash the contractor is financing. Left alone it grows, and a surety reading the WIP schedule will ask why.
- Missing a pay application cycle and letting the work pile up unbilled.
- Not billing stored materials or approved changes.
- Mistaking a late forecast for under-billing when the percent complete is overstated.
Go deeper
The full method, with more worked figures, is in the The WIP schedule: over-billing, under-billing and why they matter guide. To run it on your own numbers, use the over/under billing calculator.
Related terms
See it on real-looking numbers
Constructelligence calculates this every week for every job, read-only, from your own systems.
Try the demoJoin the private betaFrequently asked questions
What causes under-billing?
Billing less than the work done: late or missing pay applications, a schedule of values that does not match the work, stored materials not billed, or unapproved change work.
Is under-billing an asset?
Yes, it appears on the WIP schedule as an underbilling asset, but it only converts to cash when it is billed and paid.