What is the percentage of completion method in construction?

Percentage of completion recognises revenue in proportion to progress on a contract, most often measured by cost to date divided by estimated total cost (the cost-to-cost method).

The formula

Percent complete = cost to date ÷ estimated total cost. Revenue to date = contract × percent complete. Gross profit to date = revenue to date − cost to date.

A worked example

Contract · estimated cost · expected profit$2,000,000 · $1,800,000 · $200,000
Cost to date$900,000
Percent complete = 900,000 ÷ 1,800,00050%
Revenue to date$1,000,000
Gross profit to date = 1,000,000 − 900,000$100,000

Half the cost has been incurred, so half the expected profit, $100,000, is recognised.

How to read it

The method is sensitive to the estimate of total cost. If the estimate is optimistic, profit is recognised too early and a loss shows up late.

Why it matters, and where it goes wrong

Percentage of completion spreads profit across the life of a job instead of waiting until it is finished, which gives owners, lenders and managers a current picture. The price is that profit depends on forecasts.

Go deeper

The full method, with more worked figures, is in the The WIP schedule: over-billing, under-billing and why they matter guide. To run it on your own numbers, use the over/under billing calculator.

See it on real-looking numbers

Constructelligence calculates this every week for every job, read-only, from your own systems.

Try the demoJoin the private beta

Frequently asked questions

What is the cost-to-cost method?

A percentage of completion method that measures progress as cost incurred to date divided by estimated total cost.

Why is the estimate at completion so important?

Because the percent complete, and therefore the revenue and profit recognised, depends on it. A stale estimate misstates profit.