The formula
A worked example
Half the cost has been incurred, so half the expected profit, $100,000, is recognised.
How to read it
The method is sensitive to the estimate of total cost. If the estimate is optimistic, profit is recognised too early and a loss shows up late.
Why it matters, and where it goes wrong
Percentage of completion spreads profit across the life of a job instead of waiting until it is finished, which gives owners, lenders and managers a current picture. The price is that profit depends on forecasts.
- Using an out-of-date estimate of total cost.
- Applying cost-to-cost to a job where materials bought early distort the percent.
- Recognising a gain on a job that is forecast to lose money.
Go deeper
The full method, with more worked figures, is in the The WIP schedule: over-billing, under-billing and why they matter guide. To run it on your own numbers, use the over/under billing calculator.
Related terms
See it on real-looking numbers
Constructelligence calculates this every week for every job, read-only, from your own systems.
Try the demoJoin the private betaFrequently asked questions
What is the cost-to-cost method?
A percentage of completion method that measures progress as cost incurred to date divided by estimated total cost.
Why is the estimate at completion so important?
Because the percent complete, and therefore the revenue and profit recognised, depends on it. A stale estimate misstates profit.