Glossary · earned value

What is earned value in construction?

Earned value is the budgeted cost of the work actually completed: the budget multiplied by the percent complete. It puts progress in dollars so it can be compared with what was spent and what was planned.

The formula

EV = budget at completion × percent complete.

A worked example

Budget at completion$1,000,000
Percent complete (measured quantities)60%
Earned value = 1,000,000 × 60%$600,000
Planned value by now$650,000
Actual cost to date$620,000
CPI = 600,000 ÷ 620,000 · SPI = 600,000 ÷ 650,0000.968 · 0.923

With one number for progress, cost and schedule can both be measured against it: the job is over on cost (CPI below 1) and behind on schedule (SPI below 1).

How to read it

Everything depends on the percent complete. Measure it from installed quantities, not from cost spent: percent complete taken from cost always makes CPI look like 1.0.

Why it matters, and where it goes wrong

Earned value is the common yardstick behind CPI, SPI and the forecasts built on them. Without a measure of work done that is independent of cost, cost and schedule performance cannot be separated.

Go deeper

The full method, with more worked figures, is in the Earned value management for construction, explained with one job guide.

See it on real-looking numbers

Constructelligence calculates this every week for every job, read-only, from your own systems.

Try the demoJoin the private beta

Frequently asked questions

How do you calculate earned value?

Multiply the budget at completion by the percent complete. Do it by cost code and add them for the job.

Why measure percent complete from quantities?

If percent complete is taken from the cost spent, earned value always equals actual cost and the cost performance index reads 1.0 whatever is happening.