The formula
A worked example
With one number for progress, cost and schedule can both be measured against it: the job is over on cost (CPI below 1) and behind on schedule (SPI below 1).
How to read it
Everything depends on the percent complete. Measure it from installed quantities, not from cost spent: percent complete taken from cost always makes CPI look like 1.0.
Why it matters, and where it goes wrong
Earned value is the common yardstick behind CPI, SPI and the forecasts built on them. Without a measure of work done that is independent of cost, cost and schedule performance cannot be separated.
- Setting percent complete from invoices or cost, which makes earned value equal actual cost.
- Using one percent complete for the whole job instead of measuring each cost code.
- Forgetting that approved changes change the budget the percent is applied to.
Go deeper
The full method, with more worked figures, is in the Earned value management for construction, explained with one job guide.
Related terms
See it on real-looking numbers
Constructelligence calculates this every week for every job, read-only, from your own systems.
Try the demoJoin the private betaFrequently asked questions
How do you calculate earned value?
Multiply the budget at completion by the percent complete. Do it by cost code and add them for the job.
Why measure percent complete from quantities?
If percent complete is taken from the cost spent, earned value always equals actual cost and the cost performance index reads 1.0 whatever is happening.