The formula
A worked example
The job has done about 92% of the work it planned to have done, so it is behind. SPI says how far behind in value terms, not which activities are late.
How to read it
SPI drifts toward 1.0 at the end of any job, because all planned work is eventually done, so it is least useful late. Use the critical path to find which activities are actually late.
Why it matters, and where it goes wrong
SPI shows whether progress is keeping up with the plan, in the same dollar terms as cost, so cost and schedule can be read side by side on one chart.
- Relying on SPI near the end of a job, when it drifts toward 1.0 whatever happened.
- Assuming a low SPI means the finish date has moved; only the critical path decides that.
- Measuring progress by cost or time elapsed instead of by installed quantities.
Go deeper
The full method, with more worked figures, is in the Earned value management for construction, explained with one job guide.
Related terms
See it on real-looking numbers
Constructelligence calculates this every week for every job, read-only, from your own systems.
Try the demoJoin the private betaFrequently asked questions
What does an SPI of 0.9 mean?
The job has completed about 90% of the work scheduled by now, measured in budgeted value.
Does SPI tell you the project is late?
Not exactly. It measures work completed against work planned, in value. A project can have a low SPI and still finish on time if the late work is not on the critical path.