What is SPI (schedule performance index) in construction?

Schedule performance index is earned value divided by planned value. Below 1.0 the job has completed less work than was scheduled by now; above 1.0 it is ahead.

The formula

SPI = earned value (EV) ÷ planned value (PV).

A worked example

Earned value (work done, at budget)$600,000
Planned value (work scheduled by now)$650,000
SPI = 600,000 ÷ 650,0000.923

The job has done about 92% of the work it planned to have done, so it is behind. SPI says how far behind in value terms, not which activities are late.

How to read it

SPI drifts toward 1.0 at the end of any job, because all planned work is eventually done, so it is least useful late. Use the critical path to find which activities are actually late.

Why it matters, and where it goes wrong

SPI shows whether progress is keeping up with the plan, in the same dollar terms as cost, so cost and schedule can be read side by side on one chart.

Go deeper

The full method, with more worked figures, is in the Earned value management for construction, explained with one job guide.

See it on real-looking numbers

Constructelligence calculates this every week for every job, read-only, from your own systems.

Try the demoJoin the private beta

Frequently asked questions

What does an SPI of 0.9 mean?

The job has completed about 90% of the work scheduled by now, measured in budgeted value.

Does SPI tell you the project is late?

Not exactly. It measures work completed against work planned, in value. A project can have a low SPI and still finish on time if the late work is not on the critical path.