The formula
A worked example
Comparing 125 actual hours with the 240 budget would suggest the job is fine; comparing with the 108 earned hours shows crews are 16% over for what they installed.
How to read it
This needs installed quantities recorded each week, which is the step most jobs skip.
Why it matters, and where it goes wrong
Earned hours separate how much work was done from how long it took, so a crew that is installing quickly but over budget can be told apart from one that is simply behind.
- Not recording installed quantities each week.
- Using the estimate's hours per unit without allowing for changes in scope.
- Comparing earned hours across cost codes with different units.
Go deeper
The full method, with more worked figures, is in the Construction labor forecasting: from burn rate to machine learning guide.
Related terms
See it on real-looking numbers
Constructelligence calculates this every week for every job, read-only, from your own systems.
Try the demoJoin the private betaFrequently asked questions
Why compare actual hours with earned hours?
Because actual hours against the full budget ignore how much work is done. Earned hours measure what the work installed should have taken.
What do you need to calculate earned hours?
Installed quantities by cost code, and the estimated hours per unit from the estimate.