What are earned hours in construction?

Earned hours are the hours the estimate allowed for the work actually installed. Comparing them with actual hours shows productivity independently of how much work was done.

The formula

Earned hours = installed quantity × estimated hours per unit.

A worked example

Conduit: 2,000 LF at 0.12 h per LF240 hours budget
Installed to date: 900 LF, earned hours = 900 × 0.12108 hours
Actual hours charged125 hours
Productivity factor = 125 ÷ 1081.16

Comparing 125 actual hours with the 240 budget would suggest the job is fine; comparing with the 108 earned hours shows crews are 16% over for what they installed.

How to read it

This needs installed quantities recorded each week, which is the step most jobs skip.

Why it matters, and where it goes wrong

Earned hours separate how much work was done from how long it took, so a crew that is installing quickly but over budget can be told apart from one that is simply behind.

Go deeper

The full method, with more worked figures, is in the Construction labor forecasting: from burn rate to machine learning guide.

See it on real-looking numbers

Constructelligence calculates this every week for every job, read-only, from your own systems.

Try the demoJoin the private beta

Frequently asked questions

Why compare actual hours with earned hours?

Because actual hours against the full budget ignore how much work is done. Earned hours measure what the work installed should have taken.

What do you need to calculate earned hours?

Installed quantities by cost code, and the estimated hours per unit from the estimate.