What is TCPI (to-complete performance index) in construction?

To-complete performance index is the cost efficiency the rest of the job must achieve to finish within budget: the budget remaining for the work divided by the money remaining.

The formula

TCPI = (budget at completion − earned value) ÷ (budget at completion − actual cost).

A worked example

Budget at completion$1,000,000
Earned value$600,000
Actual cost$620,000
TCPI = (1,000,000 − 600,000) ÷ (1,000,000 − 620,000)1.053

The remaining $400,000 of work has to be done for $380,000, which is 5.3% better than budget, after running 3.2% worse so far.

How to read it

A TCPI well above the CPI achieved so far is a warning that the budget is probably no longer realistic. Re-forecast, and explain the gap.

Why it matters, and where it goes wrong

TCPI tests whether a forecast is believable. If the remaining work has to be done far more efficiently than the work so far, the budget is unlikely to hold, whatever the project team says.

Go deeper

The full method, with more worked figures, is in the Earned value management for construction, explained with one job guide.

See it on real-looking numbers

Constructelligence calculates this every week for every job, read-only, from your own systems.

Try the demoJoin the private beta

Frequently asked questions

What does a TCPI above 1 mean?

The remaining work has to be done more efficiently than the budget assumed to finish within budget. The further above 1.0, the less likely that is.

How is TCPI different from CPI?

CPI looks back at the efficiency so far. TCPI looks forward at the efficiency needed from now on.