The formula
A worked example
The remaining $400,000 of work has to be done for $380,000, which is 5.3% better than budget, after running 3.2% worse so far.
How to read it
A TCPI well above the CPI achieved so far is a warning that the budget is probably no longer realistic. Re-forecast, and explain the gap.
Why it matters, and where it goes wrong
TCPI tests whether a forecast is believable. If the remaining work has to be done far more efficiently than the work so far, the budget is unlikely to hold, whatever the project team says.
- Quoting TCPI without comparing it to the CPI achieved to date.
- Using the original budget when approved changes have raised it.
- Accepting a TCPI well above 1.0 as a plan instead of as a warning.
Go deeper
The full method, with more worked figures, is in the Earned value management for construction, explained with one job guide.
Related terms
See it on real-looking numbers
Constructelligence calculates this every week for every job, read-only, from your own systems.
Try the demoJoin the private betaFrequently asked questions
What does a TCPI above 1 mean?
The remaining work has to be done more efficiently than the budget assumed to finish within budget. The further above 1.0, the less likely that is.
How is TCPI different from CPI?
CPI looks back at the efficiency so far. TCPI looks forward at the efficiency needed from now on.