The formula
A worked example
The owner has paid $50,000 for work not yet done. If the contractor defaulted, that would be money the owner could not get back.
How to read it
Owners and architects test it by comparing early lines with the cost to do them. A line that is mostly overhead and profit on day one is front-loaded.
Why it matters, and where it goes wrong
Front-loading shifts risk to the owner, which is why contracts often forbid it and owners check early lines closely. A contractor that is caught front-loading damages trust on the rest of the pay applications.
- Assigning large values to mobilization or general conditions without cost to support them.
- Billing stored materials that are not properly insured or stored.
- Treating the early lines as a way to fix a cash flow problem.
Go deeper
The full method, with more worked figures, is in the Schedule of values in construction: a worked example, how to build one and how to avoid front-loading guide.
Related terms
See it on real-looking numbers
Constructelligence calculates this every week for every job, read-only, from your own systems.
Try the demoJoin the private betaFrequently asked questions
Is front-loading allowed?
Many contracts prohibit it and owners can reject a pay application that does it. Reasonable mobilization costs are usually accepted when they are real and supported.
How do you spot a front-loaded schedule of values?
Compare the value on the early lines with the cost of doing that work. Lines worth far more than their cost, early in the job, are front-loaded.