Constructelligence
Guide · pay applications

AIA G702 and G703: filling out a pay application, line by line

The AIA G702 and its G703 continuation sheet are the standard way contractors bill progress on US commercial work. The G703 lists every line of the schedule of values; the G702 summarises it into nine lines ending in the payment due. This guide walks through both, with a worked example whose numbers tie out.

Updated · 10 minute read

Key takeaways
  • The G703 is the detail by SOV line; the G702 is the nine-line summary.
  • G702 line 4 must equal the G703 column G total.
  • Only approved change orders belong in line 2.
  • Check billed against earned before you submit — under-billing is money left behind.

The G703 continuation sheet

The G703 is the detail: one row per schedule-of-values line.

ColumnWhat goes in it
A · Item no.The SOV line number
B · DescriptionThe scope of that line
C · Scheduled valueThe line’s share of the contract sum
D · From previous applicationWork completed on earlier applications
E · This periodWork completed since the last application
F · Materials presently storedStored materials not yet in D or E
G · Completed and stored to dateD + E + F, with G ÷ C as the % complete
H · Balance to finishC − G
I · RetainageIf the rate varies by line

The G702, line by line

1Original contract sum
2Net change by change orders (approved only)
3Contract sum to date = 1 ± 2
4Total completed and stored to date = G703 column G total
5Retainage on completed work and stored material
6Total earned less retainage = 4 − 5
7Less previous certificates for payment
8Current payment due = 6 − 7
9Balance to finish, including retainage = 3 − 6
A sample G702 application for payment: contract sum, completed and stored, retainage and current payment due
A G702 summary from our sample documents (invented company and figures — a later application than the worked example, so the numbers differ). Open the PDF with its G703 →

A worked example

1 · Original contract sum$3,862,000
2 · Net change by change orders$138,000
3 · Contract sum to date$4,000,000
4 · Total completed & stored$1,150,000
5 · Retainage (10%)$115,000
6 · Total earned less retainage$1,035,000
7 · Less previous certificates$862,500
8 · Current payment due$172,500
9 · Balance to finish incl. retainage$2,965,000

Before it goes out, check it against the job: if the work is really 30% complete on a $4.0M contract, $1,200,000 is earned — this application is $50,000 under-billed.

CalculatorG702 current payment due

For more inputs, a second forecast and a shareable link: the pay application & retainage calculator →

3 · Contract sum to date$4,000,0004 · Completed & stored$1,150,0005 · Retainage 10%$115,000held back6 · Earned less retainage$1,035,0007 · Previous certificates$862,500already paid8 · Current payment due$172,500this month
The worked example’s G702, top to bottom: the contract, what is complete, what the owner holds back, and — after what was paid before — the cheque this month.

Why pay applications get sent back

Every one of these is a check a system can run before submission — the WIP & billing view in the demo compares billed with earned for each job.

Check it before it goes to the owner

Most rejected pay applications fail on arithmetic or on numbers that do not match the contract. Run these checks on every application before it is signed:

  1. On every G703 line: G (completed & stored) = D + E + F, and H (balance to finish) = C − G.
  2. Column G total on the G703 equals line 4 on the G702.
  3. The scheduled values (column C) total the original contract plus approved change orders — and only approved ones.
  4. Retainage is at the contract rate, applied the way the contract says (including any reduction after a milestone).
  5. Stored materials are documented, insured and on the approved list.
  6. Percent complete by line matches what the site can show.

The G703 PDF-to-Excel converter pulls a continuation sheet into a spreadsheet and flags lines where the columns do not add up; the pay application calculator checks the payment due.

Checklist
G703 continuation sheet in Excel, filled in with example rows — columns: A Item, B Description, C Scheduled value, D Previous, E This period, F Stored, G Completed & stored, % (G/C)…
The G703 continuation sheet as it opens in Excel: example rows in italics, calculated columns shaded.
Free template · G703 continuation sheet (Excel & CSV)An Excel workbook with drop-downs, validation and formulas built in — or the same columns as a CSV for Google Sheets and Numbers.
Download Excel (.xlsx)
What this template captures

The G703 columns A to I: item, description, scheduled value, previous, this period and stored, with completed and stored, percent, balance to finish and retainage calculated.

10 columns: 6 you fill in and 4 calculated by formula and filled down 200 rows, so nothing is worked out by hand. In the Excel version, 4 columns reject entries of the wrong type (a date column only takes dates, an amount column only numbers), the header row stays frozen with filters on it, and the workbook opens on an Instructions sheet that lists every column below.

Every column, and how it is captured
ColumnTypeWhat goes in it
A ItemTextFree text.
B DescriptionTextFree text.
C Scheduled valueAmount ($)Enter the amount in dollars.
D PreviousAmount ($)Enter the amount in dollars.
E This periodAmount ($)Enter the amount in dollars.
F StoredAmount ($)Enter the amount in dollars.
G Completed & storedCalculatedCalculated: [D Previous] + [E This period] + [F Stored]
% (G/C)CalculatedCalculated: [G Completed & stored] ÷ [C Scheduled value]
H Balance to finishCalculatedCalculated: [C Scheduled value] − [G Completed & stored]
I RetainageCalculatedCalculated: [G Completed & stored] × 0.1

See it on real-looking numbers

Constructelligence is a construction intelligence platform: it reads your ERP, project and field systems read-only and does this arithmetic every week, for every job. The demo runs it on a sample eight-job portfolio.

Try the demoJoin the private beta

Frequently asked questions

What is an AIA G702?

The AIA G702 Application and Certificate for Payment is a one-page summary of a contractor's progress billing: contract sum, work completed, retainage, previous payments and the current payment due. It is certified by the architect before the owner pays.

What is the difference between G702 and G703?

The G703 continuation sheet lists each schedule-of-values line with work completed to date; the G702 summarises those totals into nine lines ending in the current payment due. Line 4 of the G702 equals the column G total of the G703.

How is current payment due calculated on a G702?

Take total completed and stored to date, subtract retainage to get total earned less retainage, then subtract previous certificates for payment. The result is line 8, current payment due.

Can unapproved change orders go on a pay application?

They should not be included in line 2, net change by change orders. Bill change orders once approved; unapproved work belongs in change order requests, not the pay application.

Why do pay applications get rejected?

Most often for arithmetic errors on the continuation sheet, scheduled values that include unapproved changes, retainage calculated at the wrong rate, or stored materials without documentation.

CI
Written by the Constructelligence teamConstruction finance and software. Worked examples use the sample demo portfolio; formulas are standard practice. Reviewed September 2026.

More in Billing & cash

Free tools for this topic: Over/under billing calculator (WIP) · Pay application and retainage calculator · G703 continuation sheet PDF to Excel

All billing & cash resources →