DCMA 14-point schedule assessment: the checks, what they catch, and software that runs them

The DCMA 14-point assessment is a set of fourteen checks on the logic and quality of a CPM schedule, published by the US Defense Contract Management Agency and now used well beyond defense work. It does not say a schedule is right. It says whether the schedule is built well enough for its float, critical path and finish date to be trusted. This guide lists the checks, the thresholds usually applied, and what to ask of software that automates them.

Updated · 8 minute read

Key takeaways
  • Fourteen checks test whether a CPM schedule is built well enough to trust.
  • Fix open ends first: they change every other result.
  • Passing means well formed, not realistic. Risk analysis tests the finish date.

The fourteen checks

Each check counts a kind of defect among the incomplete activities and compares the count with a threshold. The thresholds below are the ones commonly applied; check them against the current DCMA document and your contract, because owners sometimes set their own.

#CheckWhat it countsCommonly applied threshold
1LogicActivities missing a predecessor or a successor (open ends)5% or fewer
2LeadsRelationships with negative lagNone
3LagsRelationships with positive lag5% or fewer
4Relationship typesShare that are finish-to-start90% or more
5Hard constraints"Must start on" and "must finish on" type constraints5% or fewer
6High floatActivities with total float above 44 working days5% or fewer
7Negative floatActivities with total float below zeroNone
8High durationActivities longer than 44 working days5% or fewer
9Invalid datesForecast dates in the past, actual dates in the futureNone
10ResourcesActivities with duration but no cost or resource loadedOnly where the contract asks for loading
11Missed tasksActivities that finished later than baseline5% or fewer
12Critical path testDoes a delay added to a critical activity move the finish by the same amount?It must
13Critical path length index(Critical path length + total float) ÷ critical path lengthAbout 1.0 or more
14Baseline execution indexActivities completed ÷ activities baselined to be complete by nowAbout 0.95 or more

Checks 1 to 9 look at how the schedule is built and can be run on a single file. Checks 11 and 14 need a baseline to compare against. Check 12 needs a tool that can recalculate the schedule, which is why it is the one most often skipped.

One check worked through

Take a schedule with 400 incomplete activities. A scan finds 31 missing a predecessor or a successor, and 12 with a hard constraint:

Logic: 31 ÷ 4007.8% (over 5%)
Hard constraints: 12 ÷ 4003.0% (within 5%)

The logic check fails, and it matters more than the percentage suggests: every open end carries float that is not real, so the critical path and the finish date shown are not reliable until those 31 activities are tied in. Fix the logic first, then re-run, because closing open ends changes every other check.

CalculatorDoes this check pass?

What to look for in schedule health check software

Any tool that reads your schedule file can count open ends. The differences are in what else it does:

Question to askWhy it matters
Which file formats does it read: XER, P6 XML, MSPDI, MPP?If it cannot read your scheduler's export, you re-key or lose logic. See the scheduling software guide for formats.
Does it run all fourteen, including the critical path test and the two indexes?Many tools stop at the structural checks.
Can the thresholds be changed?Contracts and owners differ from the commonly applied figures.
Does it list the offending activities, not just a percentage?A count tells you it failed; the list tells you what to fix.
Can it compare two updates?Trend across updates shows whether quality is improving or decaying.
Does the file stay on your machine?Schedules are commercially sensitive; ask where the analysis runs.

The categories of tool are: the checks built into the scheduler itself, standalone schedule analysis products, and lightweight checkers. Our free schedule health check runs the structural checks in your browser on an exported file, which is enough to find open ends, constraints and float problems before an owner does.

What the assessment does not tell you

Passing all fourteen means the schedule is well formed. It does not mean the durations are realistic, the sequence is buildable, or the finish date is likely. A well-formed schedule with optimistic durations passes. For the likelihood of the finish, run a schedule risk analysis; for how float behaves when something slips, see the critical path worked example.

Last checked: 2026-11-15. The thresholds above are as commonly applied to the DCMA 14-point assessment; confirm against the current DCMA document and your contract before reporting against them.

Checklist
Free template · Schedule quality check log (Excel & CSV)An Excel workbook with drop-downs, validation and formulas built in — or the same columns as a CSV for Google Sheets and Numbers.
Download Excel (.xlsx)
What this template captures

9 columns: 8 you fill in and 1 picked from drop-down lists, so every row uses the same values. In the Excel version, 4 columns reject entries of the wrong type (a date column only takes dates, an amount column only numbers), the header row stays frozen with filters on it, and the workbook opens on an Instructions sheet that lists every column below.

Every column, and how it is captured
ColumnTypeWhat goes in it
Update dateDateEnter the date.
CheckTextFree text.
Activities countedNumberEnter a number.
Activities with defectTextFree text.
Share (%)PercentEnter a percentage, 0–100.
Threshold (%)PercentEnter a percentage, 0–100.
Pass (Y/N)Drop-downOptions: Y / N.
OwnerTextThe person responsible for the row.
Fixed byTextFree text.

See it on real-looking numbers

Constructelligence is a construction intelligence platform: it reads your ERP, project and field systems read-only and does this arithmetic every week, for every job. The demo runs it on a sample eight-job portfolio.

Try the demoJoin the private beta

Frequently asked questions

What is the DCMA 14-point schedule assessment?

A set of fourteen checks on a CPM schedule's quality, from the US Defense Contract Management Agency: logic, leads, lags, relationship types, constraints, float, duration, dates, resources, missed tasks, a critical path test and two indexes. It tests whether the schedule is built well enough to trust, not whether the plan is right.

What software runs a DCMA 14-point check?

Some schedulers include the structural checks, standalone schedule analysis products run all fourteen, and lightweight checkers cover the structural ones from an exported file. Ask which formats it reads, whether the thresholds can be changed, and whether it lists the offending activities.

What is a good result on a schedule health check?

Every check within its threshold, and no negative float. Treat a pass as evidence the logic is sound, not as a forecast of the finish date.

CI
Written by the Constructelligence teamConstruction finance and software. Worked examples use the sample demo portfolio; formulas are standard practice. Reviewed September 2026.