- Check retainage, pay terms, insurance, changes, notice and flow-down first.
- Reconcile each clause across every document into one table.
- Any AI flag needs a citation a person can open and confirm.
The clauses to check, and what to look for
| Clause | What to check | Common trap |
|---|---|---|
| Retainage | Rate, any reduction (for example at 50% complete), and when it is released: on substantial completion or on final | Subcontract holds more, or longer, than the prime contract holds on the GC. See retainage |
| Payment terms | Days to pay, and whether payment depends on the GC being paid | Pay-when-paid or pay-if-paid language the sub did not expect |
| Insurance | Limits, additional insured wording, waiver of subrogation, certificate timing | Limits that exceed what the sub carries, or differ from the prime contract |
| Indemnity | Scope, and whether it covers the other party's own negligence | Broad-form wording that state law limits or voids |
| Changes | Notice period, pricing method and markup caps | A short notice window that lapses before the change is priced |
| Notice and claims | Who must be told, in what form, within how many days | Notice to the wrong person, or by email when the contract says in writing |
| Flow-down | Which prime contract terms bind the sub, and whether the sub has seen the prime contract | Obligations the sub is bound to but was never given |
| Lien waivers | Which form, conditional or unconditional, and tied to which payments. See lien waivers | Unconditional waiver required before payment arrives |
| Liquidated damages and delay | Rate, the cap, and whether a time extension relieves it | Damages passed down at the prime rate without matching relief |
| Termination | Termination for convenience, cure periods, and payment on termination | No cure period, or no payment for work in place |
Which terms are enforceable differs by state and by project type, so use the table to know what to ask a lawyer, not as legal advice.
Finding every reference across a contract set
A single clause is rarely in one place: retainage can be in the agreement, a general conditions exhibit, a specification section and a pay application form, and the versions do not always agree. Three ways to find them:
- Search the text. Search each document for the clause's terms and their variants (retainage, retention, "amount withheld"). Fast, but it misses scanned pages and uses only the words you thought of.
- Read by section map. Use a checklist like the one above and read the same named sections in every document, in the same order. Slow but reliable.
- Use an AI document tool. It reads the set, returns each reference with the page and paragraph it came from, and flags documents that disagree. This is the fast route, and the citation is what makes it safe: a person must be able to open the cited page and confirm. See the AI document review guide.
Whichever you use, reconcile what you find into one table: each clause, the value in each document, and which document governs. The governing order is usually stated in the agreement.
One reconciliation, worked through
The GC is holding 5% on this sub's work from the owner but 10% from the sub. That is $36,000 of the sub's money held past what the prime contract requires, and a dispute waiting to happen. Finding it before signing is a conversation; finding it at final payment is a claim.
A review routine that sticks
- Reconcile the checklist table for every subcontract before signing.
- Keep a one-page summary per subcontract: retainage, notice days, insurance limits, payment terms.
- Diary every notice period against the contract date it starts from.
- Re-check the table when a change order or amendment is signed.
Last checked: 2026-11-15. This guide is a checklist, not legal advice; enforceability varies by state.
8 columns: 8 you fill in. In the Excel version, 2 columns reject entries of the wrong type (a date column only takes dates, an amount column only numbers), the header row stays frozen with filters on it, and the workbook opens on an Instructions sheet that lists every column below.
Every column, and how it is captured
| Column | Type | What goes in it |
|---|---|---|
| Clause | Text | Free text. |
| Prime contract | Amount ($) | Enter the amount in dollars. |
| Subcontract | Amount ($) | Enter the amount in dollars. |
| Specification | Text | Free text. |
| Which governs | Text | Free text. |
| Gap or conflict | Text | Free text. |
| Action | Text | Free text. |
| Owner | Text | The person responsible for the row. |
See it on real-looking numbers
Constructelligence is a construction intelligence platform: it reads your ERP, project and field systems read-only and does this arithmetic every week, for every job. The demo runs it on a sample eight-job portfolio.
Try the demoJoin the private betaFrequently asked questions
What should be checked in a subcontract before signing?
Retainage and its release, payment terms, insurance limits and additional insured wording, indemnity, change and notice periods, flow-down from the prime contract, lien waiver forms, liquidated damages and termination.
How do you find every retainage reference across contracts and specs?
Search the text for the term and its variants, read the same named sections in each document, or use an AI document tool that returns each reference with a page citation. Then reconcile the values into one table and identify which document governs.
What tools catch missing insurance or retainage language in subcontracts?
AI document review tools compare a contract with a checklist of required clauses and flag what is missing or different, with citations to the source text. A person should confirm each flag against the cited page.
Related guides
More in Running the business
- Change order management: stop carrying work nobody has signed for
- Subcontractor bid leveling: find the real low bid
- Construction KPIs: the 12 financial metrics that actually matter
Free tools for this topic: Change order pricing calculator · Contractor overhead recovery and break-even calculator · Construction markup vs margin calculator
All running the business resources →