- Progress tracking software turns site imagery into percent complete against BIM, the schedule, or both.
- What a tool compares against decides what you must give it, so check your model and schedule first.
- Judge a pilot on agreement with your superintendent, area by area, and on whether capture still happens in week five.
- Verified progress protects billing; it does not show whether the work cost what the estimate allowed.
How progress tracking software works
- Capture: someone walks the site with a 360° camera (often on a hard hat), or a drone flies it, on a regular cadence.
- Place: the software positions each frame on the drawings or the model, so every image has a location.
- Recognise: computer vision classifies what is in place: framing, board, ductwork, conduit, finishes.
- Compare: installed work is compared with the BIM model, the schedule, or both, to give percent complete by area, trade or activity.
- Report: dashboards and alerts show what is behind plan, and the imagery stays as a dated record.
Steps 1 and 2 are reality capture; steps 3 to 5 are what separate progress tracking from 360 photo documentation.
Five progress tracking tools, in their own words
| Vendor | What its site says | Capture | Compares against |
|---|---|---|---|
| Buildots | Describes itself as “construction intelligence to power your whole operation” and says it lets you “see what’s built and when compared to your plan”. | Offers “fully managed site captures by Buildots” (its Capture Services); the homepage does not name a device. | BIM and schedule: “connect your BIM, schedule, site data, and workforce insights into one coordinated system”. |
| OpenSpace | Describes itself as “the Visual Intelligence Platform for the built world”, with progress tracking in OpenSpace Track. | “Photos, videos, voice notes, 360° walks, drone flights”, plus walk and pilot services. | BIM coordination (“compare design and site conditions”) and planned against actual progress through a schedule integration. |
| Doxel | “Automated progress tracking to build faster.” | “The 360 camera mounted to a hard hat captures everything.” | BIM and schedule: it compares “the plan with actual progress broken down by component, system, and schedule”, starting from your BIM. |
| DroneDeploy Progress AI | “Automated construction progress tracking from drone and 360 data.” | Drone flights and 360 walkthroughs: “walk or fly your site as usual”. | Its launch post says “BIM and schedule are not required”. |
| Cupix | “Turn 360° video into as-built 4D intelligence with our digital twin platform.” | Primarily 360° video walkthroughs. | “Validate work against design and schedule.” |
Last verified 6 November 2026 against each vendor’s own website: Buildots, OpenSpace, Doxel, DroneDeploy Progress AI, Cupix. Vendors change products often; check the source before relying on any detail here.
Against BIM, against the schedule, or neither
The biggest difference between tools is what they compare the site with, and it decides what you need to give them:
| Compared with | What you need | What you get |
|---|---|---|
| BIM | A model detailed enough to recognise components in | Percent complete by element, system and area; deviations from design |
| Schedule | A schedule with activities that map to areas and trades | Planned against actual, and which activities are behind |
| Neither | Only the drawings | Visual progress and a record, with less structure |
A tool that needs a detailed model is a poor fit for a job without one, however good its demo.
How to choose: test it on a job you know
Run a pilot on a live job for four to six weeks and judge it on your own numbers:
- Does its percent complete agree with your superintendent's, area by area? Where it disagrees, who was right?
- Who captures, how long does a walk take, and does it still happen in week five?
- Does the output reach your schedule update and your pay application, or does someone retype it?
- Can you get the imagery and the progress data out if you stop using it?
- What does it cost on this job, all in? The cost guide lists the parts.
The scorecard below has these as columns, one row per vendor.
Progress is half of the money question
Percent complete feeds two numbers that decide whether a job makes money: earned revenue on the WIP schedule and the percent billed on each pay application line. Verified progress catches over-billing by subcontractors and under-billing by you. It does not, on its own, say whether the work cost what the estimate allowed; that needs cost, commitments and hours joined to it, which is what job cost forecasting does.
Next: put a number on it
Progress you can see is only half the question; the other half is whether the job is still making money. Three places to go from here:
- The cost side. The cost overrun calculator turns percent complete and cost to date into a forecast at completion.
- How AI is tested. ConstructBench is our benchmark for AI on construction work: tasks with one right answer, graded field by field.
- See it on a job. The Constructelligence demo shows a sample portfolio forecast weekly from cost, commitments and hours.
10 columns: 7 you fill in and 3 picked from drop-down lists, so every row uses the same values. In the Excel version, the header row stays frozen with filters on it, and the workbook opens on an Instructions sheet that lists every column below.
Every column, and how it is captured
| Column | Type | What goes in it |
|---|---|---|
| Vendor | Text | Vendor or subcontractor name as it appears in your vendor master. |
| Capture method | Text | Free text. |
| Who captures | Text | Free text. |
| Compares to BIM? | Drop-down | Options: Yes / No. |
| Compares to schedule? | Drop-down | Options: Yes / No. |
| Integrations you need | Text | Free text. |
| Pricing basis | Text | Free text. |
| Pilot job | Text | Free text. |
| Reviewer agrees with % complete? | Drop-down | Options: Yes / No. |
| Notes | Text | Anything that explains the row; free text. |
See it on real-looking numbers
Constructelligence is a construction intelligence platform: it reads your ERP, project and field systems read-only and does this arithmetic every week, for every job. The demo runs it on a sample eight-job portfolio.
Try the demoJoin the private betaFrequently asked questions
What is construction progress tracking software?
Software that turns site imagery, usually 360° camera walks or drone flights, into percent complete by comparing what computer vision recognises on site with the BIM model, the schedule, or both.
How accurate is automated construction progress tracking?
It depends on the job, the capture and what the tool compares against, and vendors do not publish independent accuracy tests. Pilot it on a live job and compare its percent complete with your superintendent's, area by area.
Do you need a BIM model for progress tracking?
Some tools compare against BIM and need a model detailed enough to recognise components; others compare against the schedule or the drawings only. DroneDeploy's launch post for Progress AI, for example, says BIM and schedule are not required.
Related guides
More in Progress tracking & reality capture
- 360 photo documentation for construction: routes, cadence, privacy and what to capture
- Buildots vs OpenSpace: what each says it does, and which fits your job
- Buildots alternatives and similar startups: four progress tracking tools compared, and when to pick Buildots
- OpenSpace alternatives: four reality capture and progress tools compared, and when to pick OpenSpace
- Progress tracking ROI: how to work out the return on your own job