Lien waiver log template: track conditional and unconditional waivers against every payment, with a free Excel download

A lien waiver is signed in exchange for a payment, and the usual failure is a payment made without the right waiver, or a waiver for the wrong amount. A log with one row per payment and waiver catches both. This template tracks waivers; the forms themselves are specific to each state and are not reproduced here, so use your state's form or your attorney's.

Updated · 6 minute read

Key takeaways
  • One row per payment, with the waiver type and amount.
  • Check that the waiver amount matches the payment.
  • The form is state-specific: use your state's form or your attorney's.

What the log tracks

A filled-in example

SubcontractorPay appPaymentWaiver typeWaiver amountReceivedMatches
Core Concrete4$118,500Conditional progress$118,500Nov 10Yes
Brightline Painting2$22,000Conditional progress$20,000Nov 11No: $2,000 short
Apex Electric5$64,200Unconditional progressOutstanding
CalculatorPayments without a matching waiver

Rules that keep the log useful

Collect a conditional waiver before the payment and the unconditional one after it clears, as your contract and state law require. Do not release payment against a waiver for a different amount: investigate the gap first. Keep the log with the retainage records, since final waivers and the release of retainage usually go together.

The state's rules decide the form, the wording and sometimes the timing. This log tells you what has been received; it is not legal advice on what is required.

How to fill it in

Add a row for each payment as the pay application is approved. Fill in the waiver details when the document arrives; the Matches column compares it with the payment. Filter on Outstanding before each payment run.

Checklist
Free template · Lien waiver log template (Excel & CSV)An Excel workbook with drop-downs, validation and formulas built in — or the same columns as a CSV for Google Sheets and Numbers.
Download Excel (.xlsx)
What this template captures

10 columns: 9 you fill in and 1 calculated by formula and filled down 200 rows, so nothing is worked out by hand. In the Excel version, 6 columns reject entries of the wrong type (a date column only takes dates, an amount column only numbers), the header row stays frozen with filters on it, and the workbook opens on an Instructions sheet that lists every column below.

Every column, and how it is captured
ColumnTypeWhat goes in it
SubcontractorAmount ($)Enter the amount in dollars.
Pay app no.NumberEnter a number.
Payment amountAmount ($)Enter the amount in dollars.
Through dateDateEnter the date.
Waiver typeTextFree text.
Waiver amountAmount ($)Enter the amount in dollars.
Date receivedDateEnter the date.
Matches paymentCalculatedCalculated: IF([Waiver amount]=[Payment amount], "Yes", "No")
StatusTextWhere the item stands; pick from the list so the log can be filtered and counted.
NotesTextAnything that explains the row; free text.

See it on real-looking numbers

Constructelligence is a construction intelligence platform: it reads your ERP, project and field systems read-only and does this arithmetic every week, for every job. The demo runs it on a sample eight-job portfolio.

Try the demoJoin the private beta

Frequently asked questions

What is a lien waiver log?

A record, one row per payment, of which lien waiver was requested and received, for what amount and when, so payments are not made without the right waiver.

What is the difference between conditional and unconditional lien waivers?

A conditional waiver takes effect only when the stated payment is received. An unconditional waiver takes effect when signed, whether or not payment arrives.

Should a payment be released if the waiver amount does not match?

Investigate first. A waiver for a different amount may leave the payment unprotected or release more than was paid. Follow your contract and your attorney's advice.

CI
Written by the Constructelligence teamConstruction finance and software. Worked examples use the sample demo portfolio; formulas are standard practice. Reviewed September 2026.